2022 first-class construction engineer construction gold test site equipment supply contract, one construction question, long press and like + forward + evaluation continue to be updated, click on my avatar and send a private message to me: 2022

The general terms of the complete set of equipment supply contract can refer to the general terms of the aforementioned building materials supply contract, mainly including: the name, variety, model, specification, grade of the product (compose

set of equipment) , technical standards or technical performance indicators; quantity and unit of measurement;

packaging standards and regulations on the supply and recycling of packaging materials; delivery unit, delivery method, transportation method, arrival location (including

dedicated line, dock, etc.), pick-up (received) unit; delivery (received) period; acceptance method; product price; settlement method, account opening

bank, account name, account number, settlement unit; breach of contract liability, etc.

2022 First-class Construction Engineer Construction Gold Test Center Equipment Supply Contract, First-class Construction Problem, Long Press and Like + Forward + Evaluation Continue to update, click on my avatar to send a private message to me: the general terms of the 2022 Compl - DayDayNews

In addition, the following issues must be paid attention to when signing a equipment supply contract:

1. Equipment price

2. Equipment quantity

In addition to listing the name and number of sets of equipment, it is also necessary to clearly specify the auxiliary machines, accessories, consumable spares, accessories and

installation and repair tools that accompany the host, and attach a detailed list to the contract.

3. Technical Standard

4. On-site service

The contract also requires clear

regulations on the working conditions, living benefits and expenses of supplier technicians during on-site service.

5. Acceptance and warranty.

For certain equipment that must be installed and operated before it can be found, unless otherwise specified or agreed by the parties to raise the issue of

, objections can generally be raised within 6 months from the date of operation. Whether the complete set of equipment is warranty, warranty period, and fee shall be clearly stipulated in the contract that no matter who the equipment manufacturing company is, the equipment supplier shall be responsible.