2022 first-level construction engineer management forecast test site cost management basic work, one-building finishing point prediction, long press and like + forward + evaluation continue to be updated, click on my avatar on the Wendang version to send a private message to me: The establishment of a cost management responsibility system in 2022
is the most important basic work in construction cost management; basic work also includes
(1) Unified organization of the content and format of internal engineering project cost plan. The content and format of these cost plans should be designed by each company in accordance with its own management habits and needs.
( 2 ) Establish internal construction quota of the enterprise and maintain its adaptability, effectiveness and relative advancedness, providing support for the preparation of cost plans.
(3) Establish a network for collecting market price information of means of production and necessary inquiry outlets, make good market forecasts, and ensure the timeliness and accuracy of procurement price information. At the same time, establish a list of enterprise subcontractors and supplier reviews to develop stable and good supplier relationships, and provide support for the preparation of cost plans and procurement.
( 4 ) Establish a collection, sorting, storage and use management system for cost information, reports, etc. of completed projects.
(5) Scientifically design the construction cost accounting account system, business ledger, and cost report reports to provide a unified paradigm for cost management business operations.