Yiwu Station planned total scale 11 units and 27 lines. Including the existing Shanghai-Kunming Public Speed Field 3 Channels 7 Lines, Hangzhou-Changhai Passenger Special Field 3 Channels 8 Lines, Hangzhou-Wenzhou Railway and Jinyi Passenger Special Line 3 and 4 Lines 5 Channels 12 Lines (all including the main line).
In the future, six railways including Hangzhou-Changhai High-speed Railway, Shanghai-Kunming Railway , Jinyong Railway , Hangzhou-Wenzhou High-speed Railway , Jinyi Third and Fourth Lines, and Jinyi East Urban Rail will be interconnected at Yiwu Railway Station . Yiwu Station has become the second largest station in Zhejiang Province after Hangzhou East Station , and it is also the largest railway station in county-level cities in the country.
1. Project overview
The main projects of the Shanghai-Kunming Railway Yiwu elevated station building include: 1. New elevated station building 75,000 square meters, including 16,600 square meters of entry-level station hall and supporting rooms, 5,100 square meters of overhead office equipment room, 2,300 square meters of underground exit hall, and 51,000 square meters of elevated waiting vehicles and mezzanine.
Planned construction period: 1220 calendar days, planned start date November 2022, planned completion date February 2026.
2. Bidding scope and segment division
The main contents of this tender are: Yiwu elevated station building and related projects, the north-south social channel and related projects of the station building, the Jinyi Third and Fourth Line introduction of Yiwu Station, the Hangzhou-Wenzhou Phase I Yiwu Some production and living room projects in front of the station, and the Jinyidong urban rail transit Yiwu Station related projects.
The construction section of the Yiwu elevated station building construction project of Shanghai-Kunming Railway is divided into as follows:
1, station building and related engineering standards
1, Shanghai-Kunming Railway Yiwu elevated station building construction project of Shanghai-Kunming Railway is divided into 1 standard: YWZFTJ-1 standard:
(1) Yiwu elevated station building construction project
New elevated station building Construction area 75,000 square meters, including 16,600 square meters of entry-level station hall and supporting rooms, 5,100 square meters of overhead office equipment, 2,300 square meters of underground exit hall, 51,000 elevated waiting vehicles and mezzanine Projects related to square meters, existing station yards and newly built Hangzhou temperature field to add a contracting channel.
(2) North-south social channel and related projects
synchronously implemented in the north-south social channel and the north-side yard project.
(3) The project is implemented simultaneously in the third and fourth lines of Jinyi Passenger Dedicated Line 3 and fourth lines of Yiwu station
combined with the introduction of Jinyi Passenger Dedicated Line 3 and fourth lines, the platform wall, pavement, canopy and other projects of Yiwu station 11 stations need to be implemented simultaneously (construction project, the assets are Jinyi Passenger Dedicated Line 3 and fourth lines of Jinyi Passenger Dedicated Line 11 project).
(4) The newly built Hangzhou-Wenzhou Railway Yiwu to Wenzhou section Yiwu to Wenzhou section implements the project simultaneously in Yiwu station of Yiwu station of Yiwu station of Yiwu station of Yiwu to Wenzhou section (construction project, owner is Parkson United Hangzhou-Wenzhou Co., Ltd.).
(5) New construction of production and living rooms at Yiwu Station of Yiwu Station of the Hangzhou-Wenzhou Railway to Wenzhou Railway
mainly requires the construction of the new Hangzhou-Wenzhou Railway Yiwu to Wenzhou section project within the Yiwu to Wenzhou Railway to invest in the apartment and police station living and production houses implemented simultaneously this time (construction project, owner is Parkson United Hangzhou-Wenzhou Co., Ltd.).
(6) Jinhua-Yiwu- Dongyang Urban Rail Transit Project Yiwu High-speed Railway Station
Jinhua -Yiwu-Dongyang Urban Rail Transit Project Yiwu High-speed Railway Station is an underground two-story island platform station, adopting a single column double-span box-shaped frame structure. The starting and ending mileage of the station is YDDK0+268.507~YDDK0+504.912, and the effective platform center mileage is YDDK0+412.812, and the total net length of the station is 236.405m.The 2-19th axis of the station is constructed together with the railway Yiwu elevated station building. The railway station building is a two-story frame structure and is implemented simultaneously with the station (construction project, the owner is Jinhua Jinyidong Rail Transit Co., Ltd.).
2, information standard
Shanghai-Kunming Railway Yiwu elevated station building construction project information engineering construction is divided into 1 standard: YWZFXX-1 standard:
(1) All information and related projects within this scope of Yiwu elevated station building construction project.
(2) North-South Social Channel and related projects All information and related projects within this scope.
(3) Information and related projects implemented simultaneously in the Yiwu site of Jinyi Passenger Dedicated Third and Fourth Lines (construction project, assets are Jinyi Passenger Dedicated Third and Fourth Lines Project).
(4) Information and related projects implemented simultaneously in the Yiwu station of the newly built Hangzhou-Wenzhou Railway Yiwu to Wenzhou section (construction project, owner is Parkson United Hangzhou-Wenzhou Co., Ltd.).
3. The proposed winning unit
1, YWZFTJ-1 standard
The proposed winning bidder name: China Railway Construction Engineering Group Co., Ltd. , China Railway Eleventh Bureau Group Co., Ltd. and China Railway Eleventh Bureau Group Electric Engineering Co., Ltd. Consortium
winning bid price: 1781364141 million
2, YWZFXX-1 standard
proposed winner name: Beijing Jingwei Information Technology Co., Ltd.
winning bid price: 66261766 million
3, construction supervision YWZFJL-1 standard
proposed winner name: Zhejiang Mingkang Engineering Consulting Co., Ltd.
winning bid price: 16830273 million