March 18, the reporter learned from the launch ceremony of the Jinan Municipal Transportation System's "Be brave to be the assaulter for the bid and strive to be the first Jinan regiment" labor competition. On the 18th, several road projects such as the northern section of Shanda Road, , Lao Liu Changshan Road, Cai Road North Extension, Huangtai South Road East Extension, Shunshi Road South Extension, and Shunde Road North Extension and other road projects started; Fengqi Road is fully promoted, striving to complete before the National Day; the Chejiaoshan Tunnel is open to the end of September to ensure that it is opened to traffic before the end of the year.
The southern extension of Shunshi Road is 195 meters and 3 months. is opened for
18, several road projects such as the western section of Tiechang North Road, the northern section of Shanda Road, Shuitun North Road, Lao Liu Changshan Road, the northern extension of Caitai South Road, the eastern extension of Huangtai South Road, Mingshi North Road, the southern extension of Shunde Road, and other road projects started. On the morning of the same day, the reporter came to the construction site of the south extension of Shunshi Road. It is reported that Shunshi Road extends south from Shunde Road to west, ends at Junya Road in the north, and ends at 200 meters east of Xingjihe Bridge in the east, with an implementation length of 1,218 meters.
As early as the end of 2014, the project had completed the Shunde Road to Xingji River Bridge section and the eastern section of Tiantai Sunshu Community, totaling 823.145 meters. The remaining section west of the Xingji River (195 meters) of Shunshi Road had not been constructed in the early stage due to demolition issues. At present, the Shizhong District Government and relevant offices have fully started demolition work, and the demolition work will be completed by the end of June. The construction unit plans to use three months to open up the middle section of Shunshi Road. After the southern extension of Shunshi Road and the northern extension of Shunde Road are opened to traffic, the Sunshine Shuncheng area can directly lead to the Second Ring South Road Expressway.
Fengqi Road strives to open to traffic before the 11th
Yang Feng, director of the Facilities Management Office of Jinan Municipal Transportation Commission, introduced that Fengqi Road is being fully promoted and strives to open before the 11th . It is reported that Fengqi Road is located between the Changling Mountain area of , Licheng District and of Xueshan area. It starts from Jingshi East Road in the south and ends at Feiyue Avenue in the north. The red line has a width of 50 meters and a length of 4509.538 meters. It is the main road in the city. After
is opened to traffic, the area will strengthen its ties with the central business district and the high-tech zone, and realize the connection and transfer with rail transit in the future. At present, there are more than a dozen new road projects in Jinan that have been launched and accelerated. After these projects are opened to traffic, the urban road network will be further optimized to effectively alleviate traffic congestion.
Chejiaoshan Tunnel was connected to the double holes at the end of September
Then, the reporter saw at the site of the Chejiaoshan Tunnel that the construction workers were also working in a intensive manner. It is reported that the Chejiaoshan Tunnel is located at the southernmost end of Fenghuang Road, the main line of the East Extension Expressway of Second Ring South Road, and is connected to the ramp of the South East Extension Expressway of Second Ring Road. It is an important connection channel between Fenghuang Road and the East Extension Expressway of Second Ring Road. The tunnel is 745 meters long.
tunnel adopts the form of a small clear mountain tunnel, and is arranged in both directions with six lanes. The tunnel is being accelerated, advancing about 3 meters a day. The project is planned to be completed by the end of September to ensure completion by the end of the year. Ma Xu, deputy manager of the Second Branch of Jinan Urban Construction Group, introduced that as a hub node for Fenghuang Road and the southeast extension of the Second Ring Road, after the Chejiaoshan Tunnel is opened to traffic, it will facilitate vehicles on the expressway to enter the eastern urban area and alleviate the traffic pressure near Gangjiu Road.
Weishu BRT platform was completed in the first half of the year
It is understood that the main structure of the BRT platform in the central green belt along Lingxiucheng to Weishu has been completed. After the platform is completed in the first half of the year, BRT will be available near the strange slope. It is reported that the strange slope has a large slope, and the bus climbing capacity is less than 5%, making it difficult to access the bus on strange slopes. With the opening of the south extension of Second Ring East Road and Second Ring South Road projects at the end of last year, the road conditions for buses were met near the strange slope, and the special bus lane was set up in on the Tiger Mountain Tunnel.
htmlOn March 11, the reporter learned from the Jinan Municipal Transportation Work Conference that this year, Jinan will strengthen the construction of bus passenger corridors and bus lanes networks, open BRT lines of Industrial North Road and Second Ring South Road as soon as possible, and increase the speed of bus operation on the trunk line.Beiyuan Street West extension main structure is completed by the end of the year
It is reported that the west extension construction project of Beiyuan Street Expressway is connected to the east of Second Ring West Road Kuangshan Interchange and ends at the Jingtai Expressway in the west, with a length of 5.6 kilometers and a total investment of about 2.981 billion yuan. The construction project of the west extension of Beiyuan Street Expressway will also build BRT simultaneously, and will be connected to the Beiyuan BRT corridor in the future.
The project started construction on December 28 last year, with traffic closed on January 24 this year, and construction of elevated section pile foundations began on February 22.According to the plan, the construction project of the west extension of Beiyuan Street Expressway will complete the elevated section pile foundation at the end of April this year, the main structure will be completed by the end of June 2019. After the project is opened to traffic, Beiyuan Street-Hebei Road Expressway will become the first expressway running through the east and west in Jinan, greatly alleviating the traffic pressure of Jingshi Road.
Jitai Expressway Jinan section will be completed and will be opened to traffic in June of the following year.
Jitai Expressway is an important project in the medium- and long-term plan of Shandong Province's expressway network (2014-2030). The starting point of the project route is located at the intersection of the Jinan Ring Expressway and the southern extension of the Second Ring East Road. The route ends at the northeast of the Lulai Town, Tai'an City. The entire line is 55.859 kilometers long, with a designed driving speed of 120 kilometers per hour. It is planned to be completed and opened to traffic in June 2020.
Liu Shaoshun, chairman and general manager of Shandong Gezhouba Jitai Expressway Co., Ltd., introduced that the Jinan section of Jitai Expressway is 24.6 kilometers long, with an estimated investment of 5.5439 billion yuan. At present, the Jinan section of Jitai Expressway has been fully started, with a total investment of 850 million yuan, accounting for 15.34% of the total.
It is reported that after the project is completed, it will be connected to the Second Ring East Road Expressway and Jinan Ring Expressway, effectively alleviating the traffic pressure on the Beijing-Taiwan Expressway, and adding a connection channel for the southern mountainous areas of Jinan and the Taishan tourism. It only takes half an hour from Jinan to Tai'an , which is of great significance to Jinan City to build a "high-speed integrated" and "three-ring twelve-shooting" road network. (Chief Reporter Wang Jian)