Question bank source: Safety Production Simulation Examination Yitong Official Account Mini Program 2022 Construction Employees-Civil Construction Direction-Job Skills (Constructors) Question Bank Department Construction Employees-Civil Construction Direction-Job Skills (Construc

2025/09/1408:14:46 education 1313

Question Bank Source: Safety Production Simulation Examination Yitong Official Account Mini Program

2022 Construction Employee-Civil Construction Direction-Job Skills (Constructor) Question Bank Department Construction Employee-Civil Construction Direction-Job Skills (Constructor) Examination Question Bank Must Practice Questions Before Exam! 2022 Construction Employee-Civil Construction Direction-Job Skills (Constructor) Special Work Certificate Examination Question Bank and Online Simulation Examination are based on the Construction Employee-Civil Construction Direction-Job Skills (Constructor) Examination Textbook. Construction worker-civil construction direction-job skills (construction worker) examination questions passed the production safety simulation test and randomly divided the papers.

Question bank source: Safety Production Simulation Examination Yitong Official Account Mini Program 2022 Construction Employees-Civil Construction Direction-Job Skills (Constructors) Question Bank Department Construction Employees-Civil Construction Direction-Job Skills (Construc - DayDayNews

1. [Multiple choice question] - The contents that should be considered in the preparation of general engineering safety technical measures include (). (ABCDE)

A, safety regulations for entering the construction site

B, construction electricity safety

C, safe use of mechanical equipment

D, fire and explosion-proof measures

E, protection for ground and deep pit operations

2, [Multiple choice question] The basic principles for dividing construction sections are (). (ABCDE)

A, the number of construction sections should be reasonable

B, it should be conducive to the integrity of the structure

C, there should be sufficient working face

D, and the division should be based on the dominant construction process

E, and the labor (or engineering quantity) of each construction section should be roughly equal

3, [Multiple choice question] Things to pay attention to when identifying hazard sources are (). (ABCDE)

A, fully understand the division of hazardous sources

B, clarify the methods or ways of hazardous sources

C, confirm the scope of hazardous sources

D, pay special attention to major hazardous sources, prevent the omission of

E, maintain a high alertness to hazardous sources, and continue to dynamically identify

4. [Multiple choice question] Hazardous source identification is the process of identifying the existence of hazardous sources and determining their characteristics. The methods for identifying hazard sources at construction sites include (). (ABCD)

A, expert survey method

B, safety check table method

C, on-site survey method

D, work task analysis method

E, brainstorming method

5, [Multiple choice question] Local housing and urban-rural construction departments should establish an expert database according to professional categories, and the basic conditions that experts in the expert database should meet are (). (ABC)

A, engaged in professional work for more than 15 years or have rich professional experience

B, honest and trustworthy, upright style, academic rigorous

C, have advanced professional and technical title

D, have more than 20 years or have rich professional experience

E, do things seriously and have strong sense of responsibility

6, [Multiple choice question] During the adjustment process of construction progress plan , the technical measures to compress the duration of key work are (). (BC)

A, increase the number of labor and construction machinery

B, improve construction technology and construction technology

C, adopt more advanced construction machinery

D, improve external cooperation conditions

E, adopt engineering subcontracting method

7, [Multiple choice question] When reporting and investigating production safety accidents, the principle of " four not letting go of " must be adhered to, including (). (ABDE)

A. The cause of the accident is not clear and not let go of

B. The person responsible for the accident and the employee who has not received education will not let go of

C. The unit in the accident will not let go of

D. The person responsible for the accident will not let go of

E. The person responsible for the accident will not let go of

E. The person responsible for the accident will not set up preventive measures will not let go of

8. [Multiple choice question] The removal of ground water is carried out using facilities such as settings ( ) and other facilities. (ABE)

A, drainage ditches

B, earth embankment

C, collection well

D, well point

E, gutter

Question bank source: Safety Production Simulation Examination Yitong Official Account Mini Program 2022 Construction Employees-Civil Construction Direction-Job Skills (Constructors) Question Bank Department Construction Employees-Civil Construction Direction-Job Skills (Construc - DayDayNews

9, [Multiple choice question] The content of engineering project resource management mainly includes ().(ABCD)

A, human resources management

B, material management

C, mechanical equipment management

D, technical management and fund management

E, environmental management

10, [Multiple choice question] construction and installation project fee , direct fee includes ( ). (AB)

A, direct engineering fee

B, measure fee

C, enterprise management fee

D, indirect engineering fee

E, regulation fee

11, [Multiple choice question] Construction safety accidents in construction projects can be divided into ( ) according to the severity of the accident consequences. (ABE)

A, minor injury accident

B, death accident

C, major accident

D, general accident

E, acute poisoning accident

12, [Multiple choice question] The basic content of construction technical briefing documents include (). (ABCDE)

A, construction quality requirements and quality assurance measures

B, Construction preparation work situation

C, labor arrangement and construction cycle

D, main construction methods

E, environmental safety and civilized construction and other precautions and safety assurance measures

13, [Multiple choice question] Civilized construction is to maintain a good working environment, sanitary environment and work order at the construction site. Mainly including ( ). (ABCDE)

A. Standardize the site content of the construction site, maintain the clean and hygienic working environment

B. Scientifically organize construction to make production orderly

C, reduce the impact of construction on surrounding residents and the environment

D, comply with the regulations and requirements of civilized construction on the construction site

E, ensure the safety and health of employees

14. [Multiple choice question] The obligations of construction practitioners include (). (ACD)

A, Obligation to comply with rules and regulations

B, Obligation to improve professional skills

C, Obligation to master safety knowledge and skills

D, Obligation to report safety hazards in a timely manner

E, Obligation to comply with labor discipline and professional ethics

15, [Multiple choice question] The construction task book is a comprehensive document that issues tasks to the team, implements responsibility contracting, comprehensive management and original records. It is the link between planning and implementation, which includes (). (ABC)

A, construction task order

B, limit material retrieval order

C, attendance table

D, construction schedule

E, material order

16, [Multiple choice question] construction technology briefing generally includes (). (ACD)

A, design briefing

B, contract briefing

C, construction organization design briefing

D, sub-item construction technical briefing

E, material briefing

17, [Multiple choice question] The conspicuous location at the entrance of the construction site. "Five cards" and "two pictures" should be announced, among which "five cards" refer to (). (ABCDE)

A, construction project overview card

B, safety discipline card

C, fire prevention instructions card

D, safe and no major accident card

E, production safety and civilized construction card

18, [Multiple choice question] The overall requirements for construction site management are (). (ABCDE)

A, civilized construction

B, safe and orderly

C, clean and sanitary

D, conspicuous locations at the on-site population should be announced, "five cards", "two pictures"

E, Project Manager Department should regularly inspect the construction site, listen carefully to opinions and reactions from all parties, and promptly carry out rectification

19. [Multiple choice question] Construction organization design and the preparation of special construction plans should be ().(ACE)

A, economical and reasonable

B, easy to understand

C, advanced technology

D, comprehensive range

E, leaving room for

20, [Multiple choice question] Construction organization design can be divided into ( ) according to the preparation object. (CDE)

A, post-standard construction organization design

B, pre-standard construction organization design

C, construction plan

D, total construction organization design

E, unit engineering construction organization design

21, [Multiple choice question] The basis for preparing construction progress plan includes (). (ABCE)

A, constraints

B, project construction period requirements and start-up, completion date

C, resource requirements

D, construction method

E, operation system arrangement

22, [Multiple choice question] The contents of deformation observations during deep foundation pit construction include (). (ABCDE)

A, horizontal displacement observation on the top of the support structure

B, vertical displacement, inclination, crack observation

C, vertical displacement, inclination, crack observation

D, vertical displacement observation of support structure

E, inclination observation of support structure

23, [Multiple choice question] Concrete vibration machinery is divided into ( ) according to its working method. (ABCD)

A, internal vibrator

B, surface vibrator

C, external vibrator

D, vibration table

E, all-around vibrator

24, [Multiple choice question] Concrete mixer is divided into ( ) according to its stirring principle. (AB)

A, self-fall mixer

B, mandatory mixer

C, single-sided shaft mixer

D, double-sided shaft mixer

E, drum mixer

25, [Multiple choice question] The quality of masonry depends on the quality of the raw materials and masonry methods that make up the masonry. Therefore, the correct operation method should be mastered during masonry and ( ). (ABCD)

A, horizontal and vertical

B, full mortar

C, staggered joint

D, reliable joint

E, beautiful masonry

26, [Multiple choice question] The main forms of brick masonry are (). (ACDE)

A, one-straight

B, two-straight

C, three-straight

D, plum blossom

E, all-straight

27, [Multiple choice question] The basic requirements for determining the construction sequence include (). (ABCD)

A. Must meet the requirements of the construction process

B. Must be coordinated with the construction method

C. Must consider the local climatic conditions

D. Must consider the requirements of safe construction

E. Must consider the requirements of civilized construction

28. [Multiple choice question] Structural construction drawing generally includes (). (ABCD)

A, structural design drawing directory

B, structural design general description

C, structural plan

D, component details

E, structural section

29, [Multiple choice question] Prepare a general progress plan for construction projects, mainly used to determine which of the following tasks (). (CE)

A, period quota for each single project or unit project

B, construction required construction period and calculation period

C, construction period

D, physical engineering volume of each single project or unit project

E, mutual overlap relationship of each single project or unit project

30, [Multiple choice question] The classification of network plan can be divided into ( ) according to the network plan level.(CDE)

A, time scale network plan

B, multi-target network plan

C, local network plan

D, comprehensive network plan

E, unit engineering network plan

31, [Multiple choice question] Project construction coordination is an important part of unit engineering construction deployment , including (). (ACD)

A, coordination with construction unit

B, coordination with supervision unit

C, coordination with supervision engineer

D, coordination with design unit

E, coordination with construction unit

32, [Multiple choice question] The general requirements for acceptance of construction quality of prestressed sub-projects are (). (ACD ) The construction of

A and post-slide method prestressing project should be undertaken by prestressing professional construction unit with corresponding qualification level

B and pre-slide method prestressing project should be undertaken by

C, prestressed reinforcement tensioning machine equipment and instruments should be maintained and verified regularly

D. Before pouring concrete, prestressed hidden project acceptance should be carried out

E. When concrete is poured, steam maintenance should be carried out

33. [Single choice question] ( )m or above scaffolding or set up racks, large-scale concrete formwork projects should also calculate the load bearing strength and load of the frame body and formwork to ensure safety during the construction process. (C)

A, 20

B, 25

C, 30

D, 40

34, [Single choice question] ( ) made clear provisions on security technical measures , special construction plans and safety technical briefings. (C)

A, "Construction Law"

B, " Production Safety Law "

C, " Construction Engineering Safety Management Regulations "

D, "Standard Questions"

35, [Single choice question] ( ) is to use materials reasonably and save materials on the premise of ensuring compliance with the design, safety production simulation examination, specifications and quality standards, and effectively control the consumption of materials through quota management, metrology management and other means, as well as construction quality control , avoid rework, etc. (B)

A, control of material costs

B, control of material usage

C, control of material price

D, control of material consumption

36, [Single choice question] ( ) is a "training ground" for construction personnel to improve their writing level and is also the basis for examining the writing project or technical summary after the project is completed, and it is also the basis for training for writing papers in the future. (D)

A, construction file

B, construction data

C, construction photos

D, construction log

37, [Single choice question] The following ( ) does not belong to the basis for preparing construction progress plan. (D)

A, constraints

B, project construction period requirements and start-up, completion date

C, resource requirements

D, construction method

38, [Single choice question] Which of the following is not the content included in the construction preparation (). (C)

A, technical preparation

B, fund preparation

C, mechanical preparation

D, on-site preparation

39, [Single choice question] Among the following options, the content of unit engineering construction organization design is (). (A)

A, main construction plan

B, selection of construction methods and construction machinery

C, temporary project

D, labor productivity

40, [Single choice question] Regarding the regulations that should be in compliance with the construction quality control of roof pipes after roofing pipes, the following statement is incorrect ().(A )

A, within the diameter of the pipe root diameter within the range of 500mm, the leveling layer should be applied with a circular table

B with a height of not less than 20mm, and between the surrounding pipe and the leveling layer or the waterproof layer of fine stone concrete waterproof layer, 20mm×20mm grooves should be reserved, and tightly filled with sealing material

C, and the root of the pipe Additional layers should be added around the surroundings, and the width and height should not be less than 300mm

D. Metal hoops should be tightened at the end of the waterproof layer on the pipeline, and sealed with sealing materials

41. [Single choice question] In the flat marking of beams, the marking of beams is generally a combination of centralized marking and in-situ standards. Among them, there are five necessary values ​​and one selected value in the centralized marking content. Which of the following is the selected value ( ). (B)

A, beam number

B, beam top elevation difference

C, beam top length ribs or vertical rib configuration

D, beam stirrups

42, [Single choice question] Foundation foundation engineering is a branch project. If necessary, several sub-division projects can be divided according to the current national standards ( ). (A)

A, " Unified Standard for Construction Quality Acceptance of Construction Projects "

B, "Construction Project Safety Management Regulations"

C, " Construction Project Quality Management Regulations "

D, " Mandatory Standard Supervision Regulations for Implementing Engineering Construction "

43, [Single Choice Question] Indicators for Balanced Construction do not include (). (A)

A, equilibrium coefficient

B, unequal coefficient

C, extreme difference value

D, mean square difference value

44, [Single choice question] The bearing capacity test for cement soil stirred composite foundations, high-pressure jet grouting pile composite foundations, etc., is the total number ( ), but should not be less than ( ). (C)

A, 0.5%~1%, 2

B, 0.3%~1%, 3

C, 0.5%~1%, 3

D, 0.3%~1%, 2

45, [Single choice question] Project cost control does not include (). (A)

A, control of measure fees

B, control of material fees

C, control of labor fees

D, control of management fees

46, [Single choice question] The characteristics of engineering project resources do not include (). (B)

A. There are many types of resources required for the project, large demand for

B. The amount of funds required for the project is large.

C. Imbalance in the construction process of the project

D. The impact of resources on project costs is large.

47. [Single choice question] The requirements for establishing an security management system do not include (). (B)

A, management responsibilities

B, construction method control

C, subcontractor control

D, construction process control

48, [Single choice question] The basic requirements for safe electricity use management of building construction construction, the installation and maintenance of all electrical lines and electrical equipment at the construction site must be ( ) responsible, and the regulations on construction organization design must be strictly implemented. (A)

A, certified electrician

B, construction worker

C, any electrician

D, safety officer

49, [Single choice question] The wrong statement among the characteristics of the pull-out excavator operation is (). (C)

A, earthwork

B below the excavation shutdown surface, car loading and soil throwing

C, excavation cross-section error is small

D, soil can be thrown far from both sides of the foundation pit (trough), stacking

50, [Single choice question] The construction of concrete formwork support projects with a height ( ) m or above is a relatively dangerous sub-project. (C)

A, 3

B, 4

C, 5

D, 6

51, [Single choice question] The safe use and management regulations for construction elevators. If the wind power reaches ( ) level or above, the elevator should be stopped and the cage should be lowered to the ground.(C)

A, 4

B, 5

C, 6

D, 7

52, [Single choice question] Which of the following is not included in the construction unit's on-site quality inspection? Safety production simulation exam passes one by one. ( ). (B)

A, finished product protection inspection

B, after start of construction, after process handover inspection

C, before process handover inspection

D, before resuming work after suspension

53, [Single choice question] The object of preparation of the construction plan is (). (C)

A, engineering project

B, unit project

C, branch or special project

D, building complex

54, [Single choice question] The conspicuous location at the entrance of the construction site should be announced, and the "five cards" and "two pictures" should be announced, among which the "two pictures" refer to the organizational structure of the project manager department and the list of main management personnel maps and (). (A)

A, construction general floor plan

B, construction aerial view

C, structural plan

D, building total floor plan

55, [Single choice question] The methods of actual construction site measurement methods can be summarized into dependence, hanging, quantity and (). (B)

A, look at

B, set

C, click

D, follow

56, [Single choice question] Construction management goals include quality goals, social behavior goals, etc., which of the following is not the content included in social behavior goals (). (B)

A, no public security cases

B, no major casualties

C, no fires, fire alarm accidents

D, no disturbances

57, [Single choice question] Construction management goals are an important part of unit project construction deployment, and their goals do not include (). (D)

A, quality target

B, social behavior target

C, construction period target

D, cost target

58, [Single choice question] The review content of the construction progress plan does not include (). (A)

A. Whether the progress arrangement meets the regulations of the superior

B. Whether the content in the construction schedule is omitted, whether the phased construction meets the needs of batch processing and the requirements of supporting processing

C. Whether the construction sequence arrangement meets the requirements of construction program

D. Whether the resource supply plan can ensure the implementation of the construction schedule, whether the supply is balanced, whether the resources supplied by the subcontractor meet the progress requirements

59. [Single choice question] Which of the following is not included in the content of material quality control (). (D)

A, the performance of the control material, the compliance of the standards with the design documents

B, the completeness of the control material entry acceptance procedures and quality documents

C, the compliance of various technical performance indicators of the control material, the compliance of the inspection and testing indicators with the standards

D, the mechanical properties of the control material meet the requirements

60, [Single choice question] A company purchased a batch of bulk cement at one time, and conducted witness sampling test as required, and each batch of witness sampling shall not exceed ( )t. (D)

A, 60

B, 100

C, 200

D, 500

61, [Single choice question] If a company undertakes an apartment project, the construction progress plan of the project should be prepared by (). (A)

A, construction contractor

B, construction unit

C, supervision unit

D, project manager

62, [Single choice question] A pile foundation project of a project uses casing to form holes and pour piles. According to regulations, the concrete strength level of the prefabricated pile tip should be greater than ().(D)

A, C35

B, C25

C, C40

D, C30

63, [Single choice question] When setting up a beam formwork, if the span of beam is equal to or greater than ( )m, the bottom form of the beam should be arched. If the design does not have ( A )

A, the arch height should be ____ of the full span length.

B, 4,1‰~3‰

C, 4,1‰~2‰

D, 5,1‰~3‰

E, 5,1‰~2‰

E, 5,1‰~2‰

64. [Single choice question] In the flat method of beams, some are marked as KL3(2A)300×6 "Safety Production Simulation Test One"50, then the following statement about the beam is (). (B)

A, two spans and one end cantilever

B, two spans and two spans and two spans and two spans and two spans and two spans and two spans and two spans and two spans and two spans and one end

C, the cross-sectional dimension of the beam is 300x650

D, the beam number is 3

65, [Single choice question] Which of the following is not included in the basic parameters of flow construction (). (B)

A, time parameter

B, technical parameter

C, process parameter

D, space parameter

66, [Single choice question] When mixing concrete, the commonly used feeding order does not include (). (D)

A, primary feeding method

B, cement sand wrapping method

C, secondary feeding method

D, tertiary feeding method

67, [Single choice question] The concrete structure sub-partition project can be divided into cast-in-place concrete structure sub-partition project and ( ) according to the construction method of the structure. (A)

A, prefabricated concrete structure sub-partition project

B, reinforced concrete sub-partition project

C, prestressed concrete structure sub-partition project

D, prefabricated concrete structure sub-partition project

68, [Single choice question] The basic requirements for determining the construction sequence do not include (). (D)

A. Must meet the requirements of the construction process

B. Must be coordinated with the construction method

C. Must consider the local climatic conditions

D. Must consider the requirements of civilized construction

69. [Single choice question] The characteristics of flowing water construction in different steps and rhythms do not include (). (D)

A, the flow beats of the same construction process are equal, and the flow beats of different construction processes are equal to the integer multiple of the smallest flow beats of

B, the flow steps are equal to each other, and equal to the minimum flow beat value

C, the number of construction teams is greater than the number of construction processes

D, the number of construction teams is equal to the number of construction processes

70, [Single choice question] When organizing flow construction, the time parameters do not include (). (D)

A, flow rate

B, flow rate

C, construction period

D, construction section

71, [Single choice question] When organizing flow process construction, the space parameters do not include (). (B)

A, construction layer number

B, flow step distance

C, working face

D, construction section number

72, [Single choice question] Structural construction drawings generally do not include (). (D)

A, structural design drawing directory

B, structural design general description

C, structural plan

D, structural section

73, [Single choice question] fee refers to the fees that must be paid by the government and relevant power departments. Which of the following does not fall into the scope of fees (). (B)

A, engineering pollutant discharge fee

B, environmental protection fee

C, social security fee

D, project quota measurement fee

74, [Single choice question] Quality briefing includes quality acceptance standards and ().(C)

A, Quality Manual

B, quality acceptance target

C, construction technology

D, construction method

75, [Single choice question] quality control file main, latest analysis, files to be used to express the guarantee and improve project quality, and do not include ( ) related to project quality. (A)

A, construction file

B, design file

C, process file

D, research test file

76, [Single choice question] Project construction coordination is an important part of unit project construction deployment, which does not include (). (B)

A, coordination with construction unit

B, coordination with supervision unit

C, coordination with supervision engineer

D, coordination with design unit

77, [Multiple choice question] New compressed natural gas cylinders that are in use or inflated for the first time after internal inspection should be replaced and removed as required before inflation, and can be inflated after passing the analysis. () ( √ )

78. [Judgement Question] Any project quality that fails to meet the standard must be re-repair, reinforcement or scrapped, which causes direct economic losses below the specified limit. It is called a quality accident. (×)

79. [Multiple choice question] In the dual-code network plan, the logical relationship between the front and back work is only represented. The virtual work that does not take up time or consumes resources is called virtual work . (√)

80. [Multiple choice question] Positioning and laying lines is the basis for construction projects. (√)

81. [Judgement Question] Under normal circumstances, roof construction does not divide the flow sections, and it can overlap with the decoration project. (√)

82. [Judgement Question] Project quality defects generally refer to the fact that the project does not comply with the current national or industry technical standards, design documents and quality requirements in the contract. (√)

83. [Multiple choice question] Engineering project resources are a general term for human resources, materials, machinery and equipment, technology, funds and infrastructure used in the project. (√)

84. [Judgement Question] Among the construction and installation project fees, indirect fees include measure fees and enterprise management fees. (×)

85. [Judgement Question] Construction technical briefing is a technical explanation made by a unit before the start of the project or before a sub-project construction. The purpose is to enable construction personnel to have a detailed understanding of the project characteristics, technical quality requirements, construction methods and measures and safety, so as to facilitate scientific organization of construction and avoid accidents. (√)

86. [Judgement Question] Construction quality control should implement the idea of ​​comprehensive quality management throughout the process, and use the principle of static control to perform pre-control, in-process control and post-control of quality. (×)

87. [Judgement Question] Construction quality control points refer to the key control objects, key parts or weak links that determine the "safety production simulation test" in order to ensure the quality of the operation process. (√)

88. [Judgement Question] Construction data is the data formed by a construction project during the construction process, including eight categories, including construction management data, construction technical data, completion acceptance data, etc. (√)

89. [Multiple choice question] The construction progress plan can be represented by a network diagram or a horizontal path diagram, with necessary instructions. (√)

90. [Judgement Question] The construction sequence refers to the order of construction of each unit after the project starts. (×)

91. [Multiple choice question] According to the provisions of "Quality Management System" GB/19001, any engineering product does not meet the requirements of a certain regulation is called a quality defect. (×)

92. [Multiple choice question] Fire rescue agencies should organize and direct firefighting on the scene to ensure property safety first. (×)

93. [Judgement Question] The construction quality acceptance requirements of the template sub-item construction, the number of cast-in-place structural formworks should be inspected within the same inspection batch for beams, columns and independent foundations, and no less than 5 pieces should be randomly checked for beams, columns and independent foundations.(×)

94. [Multiple choice question] The demolition procedure for templates is generally to dismantle first, to remove the non-load-bearing part first, and then to remove the load-bearing part. For the removal of major and complex templates, a mold removal plan should be formulated in advance. (×)

95. [Multiple choice question] The flow step refers to the minimum interval between two adjacent work teams successively put into work. (√)

96. [Multiple choice question] The main process of organizing flow construction: divide the construction process → divide the construction section → organize the operation team, determine the flow rhythm → continuous operation of the operation team → appropriate overlap of the work of each work team. (√)

97. [Multiple choice question] Network plan refers to a progress plan that uses network diagrams to express the task composition, work order and add working time parameters. (√)

98. [Multiple choice question] Considering that the roof waterproofing requirements are high, it is not divided into sections and is constructed in sequence. After the roof leveling layer is completed, there must be a period of maintenance and drying time before the waterproof layer can be constructed. (√)

99. [Judgement Question] Occupational health and safety refer to conditions and factors that affect the health and safety of employees and contract personnel in the workplace. Temporary staff, visitors and other personnel are not included. (×)

100. [Multiple choice question] Generalized files refer to files prepared based on the special requirements of a certain product. (×)

supports precision construction workers in all regions across the country - civil engineering direction - job skills examination questions, supports safety qualification certificate, special operation certificate , professional skills appraisal and other job question bank exercises.

education Category Latest News

At the beginning, I naively believed that there was no need to prepare anything for my children when they were promoted from infancy to infancy. After all, this is not an era of exam-oriented education, and schools would teach them from scratch. - DayDayNews

At the beginning, I naively believed that there was no need to prepare anything for my children when they were promoted from infancy to infancy. After all, this is not an era of exam-oriented education, and schools would teach them from scratch.

The interview questions for those who are promoted from kindergarten to primary school make their parents ashamed: If you don’t have something in mind, you don’t deserve to go to primary school. Your outlook on life has been refreshed.