"I can have a good sleep now, so finally I don't have to worry about having no water, cooking, or taking a bath!" Seeing the faucet at home is properly ventilated, Li Daliang, a resident of Qiaodong Community, Yangqiao Town, Boluo County, said happily. On May 14, the emergency water supply project of Bodong Six Towns officially provided water. Clean and hygienic tap water is transported to all households through pipelines, greatly alleviating the water use difficulties of local people.
It is reported that since September last year, there has been less rainfall in Boluo, and droughts have occurred in winter and spring. Among them, the drought conditions in Yangqiao and Yangcun towns are relatively prominent, resulting in residents facing the dilemma of shortage of drinking water. In order to solve the problem of drinking water shortage among about 100,000 residents in the two towns, the city and county attach great importance to it and regard it as an important part of the practical activity of "I do practical things for the people" in party history learning and education, as well as the largest emergency livelihood guarantee work in Yangqiao and Yang Village. Since the construction of the emergency water supply project of Bodong Six Towns on April 24, Yangqiao Town and relevant departments have fought continuously, and water was achieved in just 20 days. This solved the urgent need for the people to use water, and became a major example of the county's "I do practical things for the people" practical activity.
In the emergency water supply project, the water taken from Dongjiang has been treated and passed the inspection and then transported to the homes of the people.
The reverse schedule of the construction work continuously, and water supply will be achieved within 20 days
In the Tadong area where the terrain of the town is relatively high, resident Liang Zhijian introduced that the recent shortage of water use caused by drought has prompted many neighbors to install water storage tanks on the roof of their own buildings. "The lack of water and the high terrain here, we often didn't have water to come before, which made us nervous. We always wondered if there was water coming, and we had to get up in the middle of the night to store water." Liang Zhijian said with a smile. Now the water supply is relatively stable. "I can finally breathe a sigh of relief, my psychological burden has been greatly reduced, and my life and work can finally return to normal."
"In order to alleviate the shortage of water, the local party committee and government organized fire trucks to deliver water to us. Now, emergency water supply has been achieved in such a short period of time, which has helped us solve a major bottleneck that has plagued the progress of the project. "Zeng Huanlu, the head of Boluo Wanyang Zhongchuangcheng Development Co., Ltd., said that the project was settled in Yangqiao Town last year, and more than 800 workers have participated in the project construction. Now that water supply is stable, workers can also go to work with peace of mind. "From this incident, we deeply feel that Boluo's business environment is really good. The Party Committee and the government do practical things for the people, not just on the slogan, but really help us solve the difficulties."
In Qiaodong Community, Yangqiao Town, residents are washing vegetables and preparing lunch.
The two towns of Yangqiao and Yangcun located in the eastern part of Boluo have about 100,000 residents. The residents' daily water is supplied by the Yangcun Water Plant, and the only source of water intake of Yangcun Water Plant is Baoxi Reservoir. Affected by the continuous drought, the capacity of Baoxi Reservoir is decreasing. In order to ensure the water use of residents in the two towns, the two towns will implement pressurized water supply in time periods and dispersed water supply in turn from February 1. At the same time, fire trucks and sprinkler trucks were emergencyly deployed to deliver water to residents. As the drought continues, in mid-April, the water level of Baoxi Reservoir has dropped to a dead storage capacity; if there is no other water supply, residents of the two towns may face a severe situation of shutting down the supply of tap water.
Drinking water issues are a major event in people's livelihood that concerns thousands of households. In order to solve the problem of shortage of drinking water for the people, the Boluo County Party Committee and the County Government attached great importance to it and allocated special funds; the Yangqiao Town Government and relevant departments immediately launched the construction of the emergency water supply project in Bodong Six Towns. Lu Huiming, deputy secretary of the Party Committee and mayor of Yangqiao Town, introduced that the town has taken multiple measures and fought continuously, taking the solution to the water supply problem as the main livelihood of the town, actively solving the problem of "worry and hard to look forward to" the people, and promoting the practical results of party history learning and education. "This time, Dongjiang water was taken through Guanyinge Town, and after treatment, it was supplied to households." Lu Huiming introduced that the town cooperated with the county water company and others to quickly carry out clearing, equipment procurement and installation, disinfection, commissioning, personnel allocation and other work. It took only 20 days from the start of the project to the restoration of the water supply capacity of the whole town.
Boluo County Water Supply Development Corporation dispatched the project site manager Zhang Youwei, who introduced that the company sent nearly 20 staff members to be responsible for the installation and debugging of water supply facilities. Zhang Youwei introduced that after the self-inspection met the sanitation standards for drinking water, the water supply began to be tested in the early morning of May 13. During this period, everyone carried out emergency repairs on some problems such as water leakage in the pipeline that occurred during the test water supply, and worked overnight until after 2 a.m. to achieve trial water supply. After passing the inspection by the disease control department, the project will provide water formally at noon on May 14.
After the Boluo Wanyang Crowd Creation City project, workers are washing vegetables.
"Living water" is coming, and residents' enterprises like
"I feel at ease when I get water, and I don't have to go more than 10 trips a day to load well water." You Xiaohong, who runs a restaurant next to National Highway 205, said happily that the water quality and pressure after water is good, "The water is very clean and the water flows are quite large." You Xiaohong According to the introduction, due to the operation of catering, the daily water consumption is large. When there was no water, the couple had to ride a motorcycle to a place hundreds of meters away to get ground water. "There is at least 20 buckets of water a day, and it will take more than an hour to get it. Now if there is water, there is no need to worry about it."
Washing vegetables and dishes... At noon, Zhu Guiying, a resident of the town, was busy in the kitchen. Because of the restoration of water supply, she was able to do her work with ease. "There was no water at the end of the two days ago, and it was mainly due to the fire trucks to deliver water. More than 10 buckets at home were used to store water." Zhu Guiying introduced that the water cutoff caused many inconveniences to life. "It is not convenient to cook and take a bath. Now it is convenient to have water, and cooking is much faster!"
operates for 20 consecutive days, and the emergency water supply project is completed and water supply is achieved.
In the Tadong area of the town, resident Liang Zhijian introduced that the recent drought has caused a shortage of water use, which has prompted many neighbors to install water storage tanks on the roof of their own buildings. "The lack of water and the high terrain here, we often didn't have water before, which made us nervous. We always wondered if there was water. We had to get up in the middle of the night to store water." Liang Zhijian smiled and said that the water supply is relatively stable now. "I can finally breathe a sigh of relief, my psychological burden has been greatly reduced, and my life and work can finally return to normal."
"In the past, in order to alleviate the shortage of water, the local party committee and government organized fire trucks to deliver water to us. Now, emergency water supply has been achieved in such a short time, which has helped us solve a major problem of plaguing the project's progress. Bottleneck." Zeng Huanlu, head of Boluo Wanyang Zhongchuangcheng Development Co., Ltd., said that the project was settled in Yangqiao Town last year, and more than 800 workers have participated in the project construction. Now that the water supply is stable, workers can also go to work with peace of mind. "From this incident, we deeply feel that Boluo's business environment is really good. The Party Committee and the government do practical things for the people, not just on the slogan, but really help us solve the difficulties."
It is reported that the current daily water supply capacity of the project is 20,000 m3, which can basically meet the daily water use of residents of Yangqiao and Yangcun. Next, Yangqiao Town will further refine and improve the water supply emergency plan to effectively ensure the people's daily drinking water needs. At the same time, the town will start the rectification of the pipeline system, renovate the old pipelines in the town, and further improve the local production and living water conditions.
Text and pictures Huizhou Newspaper All-Media Reporter Zhu Liting Li Yanwen He Xiaoshan Correspondent Pan Wenzhong