Handling of the quality disputes on the completion project of the first-class construction engineer regulations in 2022, First-class Construction Engineer Notes, Long press and like + forward + evaluation continue to be updated, click on my avatar on the Wendang version and send

2025/06/0217:53:33 education 1773

2022 first-class construction engineer regulations golden test site handling of the quality of the completed project, Yijian Xueba notes, long press and like + forward + evaluation continue to be updated, click on my avatar on the Wendang version to send a private message to me: 2022

 The quality of the construction project does not comply with the agreement due to the contractor's fault, the contractor refuses to repair, rework or rebuild, and the contractor requests to reduce the payment of the project price, it should be supported.

 If the contractor has any of the following circumstances and causes defects in the quality of the construction project, he shall bear the fault responsibility of : (1) The design provided is defective; (2) The building materials, building components and equipment provided or designated to be purchased by

does not comply with the mandatory standards; (3) Directly designate the subcontractor to subcontract professional projects.

 The construction project can only be delivered and used after passing the completion of the construction project. If the contractor claims rights without completion acceptance and the quality of the construction project is deemed to be delivered without authorization (it is deemed to be recognized as the quality of the construction project) and claims the right on the grounds that the quality of the use does not comply with the agreement, it will not be supported; however, the contractor shall bear civil liability for the quality of the foundation project and the main structure of the ② within the reasonable service life of the construction project.

projects that have not been completed and accepted will not be renovated, but there are two exceptions: ① foundation engineering and ② main structure.

Handling of the quality disputes on the completion project of the first-class construction engineer regulations in 2022, First-class Construction Engineer Notes, Long press and like + forward + evaluation continue to be updated, click on my avatar on the Wendang version and send  - DayDayNews

Completion acceptance filing time and submitted documents

 The construction unit shall submit the completion acceptance report to the construction administrative department for filing within 15 days from the date of completion acceptance.

 The project quality supervision agency shall submit a project quality supervision report to the filing authority within 5 days from the date of completion and acceptance of the project.

 If the filing authority finds that the construction unit violates the national construction project quality management regulations during the completion acceptance process,

shall order it to stop using the completion acceptance filing documents and reorganize the completion acceptance within 15 days after receiving the completion acceptance filing documents.