On October 21, the official website of the Municipal Rail Group released a second notice of environmental impact assessment information for Metro Line 8 project, soliciting opinions from the public. The "Draft for Soliciting Opinions for Project Environmental Impact Report" relea

On October 21, the official website of

Municipal Rail Group released the second announcement of the environmental impact assessment information of

Metro Line 8 project, and

is for public comments.

"Draft for soliciting opinions on the project environmental impact report" released this time,

released more details of Line 8.

map/Yao Yujia

■ Reporter Yang Chunyan

In June 2019, the National Development and Reform Commission issued the "Approval on Xi'an Urban Rail Transit Construction Plan (2018-2024)", agreeing to the planning and construction of Line 1 Phase 3 and Line 2 II There are seven projects including Phase 8, Phase 10, Phase 14, Phase 15, Phase 16, Phase 1, and Phase 16, with a total length of about 150km.

total length 49.896 kilometers

8 is the only loop line of the network

In the third phase planned line network, the most popular among citizens is Metro Line 8. As the main skeleton line of Xi'an urban rail transit network, Metro Line 8 is the only ring line in the network.

Line 8 runs through 5 administrative regions including Yanta District , Xincheng District, Baqiao District , Weiyang District , Lianhu District , as well as high-tech zone, Qujiang New District , champagne Ecological Park, Economic Development Zone 4 new development areas including the district.

According to the latest environmental impact assessment report, Metro Line 8 is 49.896km long, all of which are underground lines, along Zhangba East Road, Yanzhan Road, Yannan Fourth Road, Hanyao Road, South Third Ring Road, Changming Road, Xingfu Forest belt, Guangyuntan Avenue, Xiangba 1st Road, Fengcheng 2nd Road, Zhuhong Road, Daxing Road, West Second Ring Road, Fenghui Road and Tangyan Road were arranged.

The minimum station spacing is 790 meters

transfer function highlights

Subway Line 8 has 37 stations, including 18 transfer stations. The maximum station spacing is 2529m, located in the area between Mingguang Road and Fanjia Village, the minimum station spacing is 790m, located in the area between Electronics and Zhengjie Street and Dongyi Road, with an average station spacing of 1.349km. Line 8 forms multiple transfers with the lines in the network, which is an important transfer route in the network, and has outstanding transfer function.

reporter sorted out the transfer stations of Line 8 and found that the transfer stations of Electronic City Station, Wangjiafen Station and Line 7 transfer, Dongyi Road Station and Line 11 transfer, Exhibition Center Station and , Municipal Library Station and Line 2 transfer, Qujiangchi West Station, Yujiazhai Station and Line 4 transfer, Changming Road Station, Xintaoyuan Station and Line 5 transfer, Wanshou South Road Station, Zhijiazhai Station and Line 6 transfer Pass, transfer to Guangtaimen Station, Yanpingmen Station and Line 3, transfer to Baozicun Station and Line 19, transfer to Yangjiazhuang Station and Line 10, transfer to Kaiyuanmen Station and Line 1, and transfer to Zhiliu Road The station transfers to Line 6 and Line 11.

Metro Line 8 sets up the Changming Road depot on the east side of Changming Road and the south side of Dongyue Road, and sets up the Huanyuan Middle Road parking lot on the north side of Fengcheng 5th Road and the west side of Beichen Avenue. A new main substation was built across the line, sharing Line 1 Huancheng Xiyuan, Line 2 Convention and Exhibition Center, and Line 5 Rongjiazhai Main Substation. The control center is located in the Changming Road Vehicle Depot plot on Line 8 Changming Road.

uses A-type vehicles

full-line large-scale transportation

According to the environmental impact assessment report, Line 8 will use domestic A-type vehicles, all of which adopt 6 marshalling schemes, 4 movements and 2 tows, and the maximum running speed of the train is 80km/h.

According to the passenger flow forecast of Line 8 and the analysis of the network service level matching, Line 8 adopts the operation mode of one large intersection on the entire line, and the operating time is expected to be from 5:30 to 23:30 am, and the total operation is 18 hours throughout the day.

According to the schematic diagram of the environmental impact assessment report, the inner ring of Line 8 runs clockwise and the outer ring runs counterclockwise.

Optimized and adjusted the settings of local line stations

Relevant departments further investigated and analyzed factors such as environmental sensitive points, geological conditions, engineering construction conditions, and local relevant departments along the line, and further studied and optimized and adjusted the settings of local lines and stations.

In order to drive the development of surrounding plots, facilitate surrounding passenger flow, and support surrounding commercial development, and in combination with the needs of Lianhu District Government, this design adds one station - Dabaipo Station - in the largest station spacing section of the entire line (Hongmiaopo-Xiaobaipo section).The northeast quadrant of Dabaiyang Station is the office building and parking lot of Shaanxi Communications Service Co., Ltd. (Zhongjie Science and Technology Branch); the southeast quadrant is the Blue Flower City Community; the southwest quadrant is the private house along the railway and the railway work team room; the northwest quadrant is the park mansion community.

is a reasonable layout of line stations, effectively connecting many passenger flow distribution points, ensuring the safety and feasibility of the project, and at the same time, starting from factors such as small interference with surrounding buildings. In this design, the route of the Qujiang Chixi to Yanxiang section is from the planning environmental impact assessment stage Yannan Fifth Road was changed to Hanyao Road. After adjustment, the line was straight and did not penetrate the existing vibrating buildings. The project was highly implemented and the operating conditions were better. The rest of the road sections have not changed.

3 cultural relics protection units along the line

will use shield construction to reduce the impact

According to the draft for environmental impact assessment, Metro Line 8 involves Han Chang'an City Ruins (the ground ruins of Han Chang'an City and the Tangbiyong site), and the Chang'an City Ruins of Sui and Tangtang Tang Tang Tang Tang ( Yanpingmen ruins and Temple of Heaven ruins), Duling 3 cultural relics protection units.

8 will pass through the Han Chang'an City Ruins in the form of a tunnel to control the construction control zone of in the Han Chang'an City Ruins, the Sui and Tang Dynasties construction control zone of and the landscape coordination zone, the Sui and Tang Dynasties construction control zone, the Duling general protection scope, construction control zone and environmental coordination zone.

Before the construction of these areas, the subway will carry out detailed archaeological exploration and investigation work, and use the sectional tunnel to pass through the Han Chang'an City ruins. The sectional tunnel construction adopts the shield construction method with the least environmental impact and the most effective settlement control. Reduce the impact on the site, while trying to increase the burial depth to reduce the impact of vibration on cultural relics.