Leju New Media 2022-10-11 15:08. Leju New Media Nanchang News On October 10, Zhengrong Jinmao Meili Yunjing released the latest project progress in September.

2025/05/1310:12:34 home 1147

Leju New Media 2022-10-11 15:08 2473Read

Leju New Media Nanchang News On October 10, Zhengrong Jinmao Meili Yunjing released the latest project progress in September. So far, there are only 2 months left before the full delivery of the first batch of the project.

Leju New Media 2022-10-11 15:08. Leju New Media Nanchang News On October 10, Zhengrong Jinmao Meili Yunjing released the latest project progress in September. - DayDayNews

1# main structure is completed, masonry is completed, outer powder is completed, and window frame installation is completed.

2# floor paint is completed, fine water and electricity is completed, panel sealing is completed, waterproof is completed, leveling is completed; 2-27 primer is completed, indoor and public areas tiles are completed, towel rack , tissue rack and other small hardware are installed, entrance door installation is completed, wooden floor installation is completed, cabinet is installed, and indoor door frame is completed.

3# floor paint is completed, fine water and electricity is completed, plate sealing is completed, waterproof is completed, and leveling is completed; 2-27 primer is completed, indoor and public areas tiles are completed, towel racks, tissue racks and other small hardware are installed, entrance doors are installed, cabinet cabinets are completed, and indoor door frames are completed.

5# floor paint is completed, fine water and electricity is completed, plate sealing is completed, waterproof is completed, leveling is completed; 2-27 primer is completed, indoor and public areas are completed, tissue racks and other small hardware are installed, and entrance doors are installed.

6# floor painted inside and outside, aluminum alloy windows installed, elevator installation, internal insulation completed, flooring completed, and paint completed 60%.

7# floor painted inside and outside, aluminum alloy windows installed, elevator installation, internal insulation completed, flooring completed, and paint completed.

11# floor painted inside and outside, aluminum alloy windows installed, elevator installation, wall insulation mortar completed, and floor completed.

12# floor paint is completed, fine water and electricity is completed, plate sealing is completed, waterproof is completed, and leveling is completed; 2-27 primer is completed, indoor and public areas tiles are completed, tissue racks and other small hardware are installed, entrance doors are installed, cabinets are installed, and indoor door frames are completed.

13# floor painted inside and outside, aluminum alloy windows installed, elevator installation, internal insulation completed, and floor completed.

15# floor painted inside and outside, aluminum alloy windows installed, elevator installation, internal insulation completed, and floor completed.

16# floor paint is completed, fine water and electricity is completed, plate sealing is completed, waterproof is completed, leveling is completed, 2-27 primer is completed, indoor and public areas are completed, tissue racks and other small hardware is installed, and entrance doors are installed.

17# floor paint is completed, fine water and electricity is completed, plate sealing is completed, waterproof is completed, leveling is completed, 2-27 primer is completed, indoor and public areas tiles are completed, tissue racks and other small hardware are installed, and cabinet cabinets are completed.