Ziyang Net News (all-media reporter Su Qiupan and Wu Xiaoming) Since its establishment, Ziyang Linkong Economic Zone has been committed to promoting the implementation of talent policies and vigorously attracting all types of talents to Linkong. Economic zone agglomeration. The talent apartment project is an important supporting project for attracting, retaining and serving talents in the Airport Economic Zone. How is the current progress of the project? On the 29th, reporters learned from Ziyang Airport Investment Group Co., Ltd. that the second phase of the Ziyang Airport Economic Zone Talent Service Center project has been capped.

[Source: Ziyang.com] Ziyang.com (all-media reporter Su Qiutan and Wu Xiaoming) Since its establishment, Ziyang Linkong Economic Zone has been committed to promoting the implementation of talent policies and vigorously attracting all types of talents to the Linkong Economic Zone.  - DayDayNewshtml On June 29, the reporter saw at the second phase construction site of the Linkong Talent Service Center project that three tower cranes were busy operating, and the workers were performing their duties and busy constructing the secondary structure.

The Linkong Economic Zone Talent Service Center has two phases. The first phase has B1-B4, a total of 4 buildings. B1 and B2 are used for accommodation. There are a total of 456 houses with a building area of ​​39-123 square meters. Buildings B3 and B4 For commercial use, each has 3 floors of commercial housing; in the second phase, there are A1-A4, a total of 4 buildings. A1-A3 are used for housing, with a total of 318 houses, with a housing area of ​​46-121 square meters. Building A4 is for commercial use, with 5 storey commercial housing.

[Source: Ziyang.com] Ziyang.com (all-media reporter Su Qiutan and Wu Xiaoming) Since its establishment, Ziyang Linkong Economic Zone has been committed to promoting the implementation of talent policies and vigorously attracting all types of talents to the Linkong Economic Zone.  - DayDayNews

"There are one to three housing units, which can meet the needs of talents with different needs." He Li, project leader of the Talent Service Center of Hong Kong Investment Group, told reporters that the talent service center project will also divide the houses into rental houses and houses for sale. People who come to work in the airport economic zone can choose according to their needs. In the commercial building, you can also eat, go shopping, and watch movies, which can meet everyone's leisure and entertainment needs.

[Source: Ziyang.com] Ziyang.com (all-media reporter Su Qiutan and Wu Xiaoming) Since its establishment, Ziyang Linkong Economic Zone has been committed to promoting the implementation of talent policies and vigorously attracting all types of talents to the Linkong Economic Zone.  - DayDayNews

"The first phase has fully entered the ±0 (main above-ground construction) stage. Building B2 of the first phase has now been built to the 10th floor. The entire first phase of the project is expected to be completed in September 2023 next year." According to He Li, At present, the second phase of the project has been fully capped, and buildings A1, A2, and A4 have entered the secondary structure work and are expected to be completed in September 2023; the secondary structure of building A3, which is a rental house, has been completed and fine decoration work is in progress. We will strive to complete the delivery of 100 households by August 30, 2022.

It is reported that the Linkong Economic Zone Talent Service Center project will start construction in July 2021. The total investment of the project is 799 million yuan, with a land area of ​​about 37.41 acres. It is about 1 km from Chengzi Avenue and about 1 km from the Linkong Station of Rail Transit Line 18. km, 28 kilometers from the Tianfu International Airport rail transit station (only 15 minutes by car), and 10 kilometers from the three rail transit stations in Ziyang central city (only 15 minutes by car). The transportation is very convenient and can meet the travel needs of quickly reaching Ziyang central city, Tianfu International Airport and Chengdu Tianfu New District.