2022 first-level construction engineer management forecast test point cost control, one-building finishing point prediction, long press and like + forward + evaluation continue to be updated, Wendang version click on my avatar to send a private message to me: 2022
cost control basis
(1) contract file
(2) cost plan (including both the predetermined specific cost control goals, as well as measures and plans for implementing control goals, it is a guide file for cost control)
(3) progress report (providing information on the actual completion of the project corresponding to the time node, the actual expenditure of the project cost , etc.)
(4) Project changes and claims information (changes)
(5) Market information of various resources (calculate the cost deviation of the project, estimate the development trend of the cost).
cost control program
To do a good job in cost process control, standardized process control programs must be formulated. There are two types of control programs in the process of cost control, one is the management behavior control program, and the other is the indicator control program. The management behavior control program is the basis for the entire process of cost control, and the indicator control program is the focus of process control of cost. The two programs are both relatively independent and interconnected, complementary and restrictive.
cost process control method (segment of quantity and price)
1) Control of labor costs
implements "segment of quantity and price" and comprehensively determines the number of labor and unit price according to a certain proportion of the fixed working days, and controls it through labor contract .
Strengthening labor quota management , improving labor productivity, and reducing labor days for engineering labor consumption are the key means to control labor expenses.
2) Control of material charges
quantity adopts fixed quota control, indicator control, measurement control, lump control/small and sporadic materials; the material price is mainly controlled by the material procurement department. Controlling material prices is mainly through grasping market information and controlling procurement prices through bidding and inquiry.
3) Control of machine usage fees
First of all, the combination method of construction machinery adopted should be determined based on the project characteristics and construction conditions. When determining which combination method to adopt, the construction needs should be met first, and secondly, the cost and comprehensive economic benefits should be taken into account. Construction machinery usage fee is mainly determined by the number of shifts and the unit price of shifts.
4) subcontract contract control
project manager department should determine the scope of the project that needs to be subcontracted in the early stage of determining the construction plan. The factors that determine the scope of the subcontract are mainly the professionalism and project scale of the construction project. The control of subcontracting fees mainly involves the inquiry of subcontracting projects, the conclusion of equal and mutually beneficial subcontracting contracts, the establishment of a stable subcontracting relationship network, and the strengthening of construction acceptance and subcontracting settlement.