22 The basis for the preparation of the first-level construction engineer management gold test point cost plan, the notes of the first-level construction master, press and hold to like + forward + comment to continue to update, click on my avatar in the Wendang version to send me a private message: 2022

★★Test point 1: The basis for preparing the cost plan:

(1) Contract documents

(2) Project management implementation plan

(3) Relevant design documents

(4) Price information

(5) Relevant quotas

(6) Cost information of similar projects

The basis for the preparation of the cost plan for the 22-year first-class construction engineer management gold test point, the notes of the first-level construction master, long press to like + forward + comment for continuous updates, click on my avatar in the Wendang version  - DayDayNews

★Test point 1: Preparation method of cost plan:

 Prepare construction cost plan according to project progress. There are 2 representation methods: one is the cost plan prepared on a monthly basis on the time scale network diagram; the other is to use the time-cost curve (S-shaped curve) represents

. The S-shaped curve (cost planning value curve) must be wrapped in a "banana chart" composed of a curve in which all work starts at the earliest start time and all work starts at the latest must-start time. "Inside.

 Generally speaking, all work starts at the latest start time, which is beneficial to saving money and loan interest, but at the same time, it also reduces the guarantee rate of project completion on schedule.