Hegang high -speed second -phase tunnel section
is currently connected throughout the board! The
project is expected to open to traffic in the first half of next year.
only takes 30 minutes from Xiangzhou to Pingsha.
Pingsha New City to Gongbei
40 minutes can be available!
Xiaobian learned from Zhuhai Transportation Group on the 18th that the tunnel section in the second phase of the Hegang Expressway project was fully opened at the end of March. 75% has been set up. The second phase of Hegang Expressway is sprinting towards the goal of "penetrating the end of the year and ensuring opening up in the first half of next year".

Hegang High -speed Chicken Gate Bridge construction site. Zhong Fan/Photo
At present,
has made significant progress in the second phase of the second phase.
↓ ↓
Hegang high -speed tunnel section
is currently connected to
Hegang Expressway. Transfer Huang Mao through interconnection Cross -sea channel. Among the
, the second phase of the Hegang Expressway starts from the entrance of the entrance and exit of Dalin Interchange of Jinwan at the highway at the airport, all the way to the west, the intersection of the intersection with Zhuhai Avenue (near Beishui intersection), set up a Pingsha entrance ramp, and a high column near Pingsha New City has a high bar. The entrance and exit ramps are connected to the high -speed and Huangmao sea cross -sea channel.

This high -speed crossing Lianwan Mountain has two tunnels, which are the Weidong No. 1 tunnel with a total length of nearly 2 kilometers and the 450 -meter Weidong No. 2 tunnel. At the end of March in HTML, the Weidong No. 2 tunnel penetrated, marking the full connection between the Hegang high -speed tunnel section.
Hegang High -speed Phase II
is expected to penetrate
in November. It is reported that the construction unit's China Railway Tunnel Bureau is stepping up the construction of the tunnel's elevation structure. And the rapidly Weidong tunnel, the grassroots grassroots have been completed. After the construction of the waiting project is ending, the tunnel will also laid asphalt pavement and complete the installation of the auxiliary facilities.

Hegang Expressway Weidong Tunnel construction site. Zhong Fan/Photo
Hegang High -speed Phase II Phase II's six lanes, most of which are bridges. At present, the bridge section includes all interchange interchange along the line. The penetration of the tunnel section also allows the construction of the project to enter a new round of orgasm. The prefabricated beams are continuously reached through the tunnel to carry out the work surface. The builders are sprinting for the last 25%of the prefabricated beam stand, and strive to complete the around July.

Hegang High -speed Chicken Gate Bridge project renderings.
Chicken Hill Gate Bridge is a key node for the construction of the whole line. In order to meet the needs of navigation under the bridge, the main bridge uses a span combination of "110 meters+200 meters+1110 meters" to cross the chicken crying water channel. The method of pouring. is currently 58%of the pouring beams, and it is expected that the second phase of the Hegang Expressway Phase II will penetrate in November.

Hegang High -speed Chicken Gate Bridge construction site. Zhong Fan/Photo
, as a large traffic artery of Zhuhai, the construction of the second phase of the Hegang Expressway will greatly reduce the commute time in the city. According to the estimates of the construction unit, after the Hegang Expressway of 100 kilometers per hour is completed, the citizen can reach Pingsha Town from the fastest 30 minutes from Xiangzhou District; it takes about 40 minutes of from Pingsha New City to Gongbei.
is completed with
in 2024,
Hegang high -speed cooperation with
,
Hong Kong -Zhuhai -Macao Bridge can go west to Jiangmen via
highway. 1
Development Speed up!