Civil Engineering General Contracting Responsibility Scope:
completes the structure and secondary structure of the garbage room;
completes the interior decoration and door and window installation of the garbage room (the detailed decoration method shall be subject to the construction drawings of the final design institute);
is responsible for the equipment transportation channel of the garbage room ( Reservation, reinforcement and sealing (including primary and secondary structures);
is responsible for the opening and reinforcement of all rear openings on primary and secondary structures (one side or diameter is greater than or equal to 300mm);
is responsible for all reservations The sealing work (including fireproof sealing) outside the hole and the back opening casing;
the production of all garbage room equipment foundations and the embedded work of structural embedded parts.
Electromechanical subcontracting responsibility scope:
is responsible for the drilling work of all rear openings (one side or diameter is less than 300mm) on primary and secondary structures;
the reserved and buried work of related electromechanical pipelines;
in the garbage room Ventilation, air conditioning, water supply and drainage, and lighting are constructed by mechanical and electrical subcontractors; other power boxes are connected to the pile head of the garbage compressor power box (supply A), and are responsible for the installation of the distribution box.
is a professional subcontractor for grounding projects. The electromechanical subcontractor leads the flat iron to the predetermined grounding point on the drawing or reserves an equal potential box according to the drawing.
Garbage room subcontracting responsibility scope:
completes the deepening of the drawings of the garbage room;
provides structural embedded parts and on-site guidance on the embedded structural parts;
If available, the supply, installation, commissioning and acceptance of garbage compressors ;
Pipeline construction after removing the pile head from the power box.
If yes, the lightning protection of the garbage compactor is grounded.
If applicable, supply, installation, debugging and acceptance of the garbage cold storage;
completes the garbage room acceptance work and assists in completing the sanitation acceptance work.
Description: The division of the interface is closely related to the division of tender sections, system forms, and project formats. The municipal interface is also related to local municipal policies. Refer to this interface to pay attention to the actual situation of your project. If you think there is a better division, please suggest the following Leave a message for your reference.