100% question bank provides (civil construction) examination questions, 8 (civil construction) examination prediction questions, 8 (civil construction) examination real questions, 8 (civil construction) examination questions, 8 (civil construction) certificate examination question bank, etc. , provides online questions and brushing questions, online mock exams, help you pass the exam easily.
1. During the construction process, various factors affecting the cost of construction projects are strengthened and various effective measures are used to correct them. This is () in the cost management of construction projects.
A.Construction cost control
B.Construction cost planning
C.Construction cost prediction
D.Construction cost accounting
Answer:A
Analysis: Strengthen management of various factors affecting the cost of construction projects, and use various effective measures to correct it. This is the construction cost control in the cost management of construction projects.
2. The following shall be borne by the contractor ().
A. The contractor's construction site assets
B. Caused casualties of the contractor due to project damage
C. Project cleaning and repair costs
D. The contractor's rushing costs
Answer: B
Analysis: The losses caused by force majeure during the performance of the construction contract, the following should be borne by the contractor due to project damage
.
3. According to the purpose and requirements of the claim, engineering claims can be divided into ().
A. Claims stipulated in the contract and claims not stipulated in the contract
B. Period claims and expense claims
C. Project claims and business claims
D. Single claims and total claims
Answer: B
Analysis: According to the different purposes and requirements of the claim, engineering claims can be divided into construction period claims and expense claims. Depending on the nature of the claim event, engineering claims can be divided into project delay claims, accelerated construction claims, project change claims, contract termination claims, unforeseen adverse conditions claims, force majeure events claims, and other claims.
4. Regarding the special handling of the contract price adjustment during the construction period delay period, the correct statement is ().
A. The construction period delay caused by the organizer, the laws and regulations change during the period will be adjusted. The contract price will be adjusted.
B. The construction period delay caused by the contractor, the laws and regulations change during the period will be changed. If the contract price increases, the price will not be adjusted.
C. The construction period delay caused by the contractor, the laws and regulations change during the period will be changed. If the contract price increases or decreases, the price will not be adjusted.
D. The construction period delay caused by the contractor, the laws and regulations change during the period will be changed.
Assay: B
Analysis: Special treatment of the construction period adjustment during the period will be handled. If the laws and regulations change during the period will be changed, the price will not be adjusted.
5. Among the methods of cost control for construction projects, different methods can be used for deviation analysis. Commonly used are horizontal diagram method, curve method and ().
A. Ratio method
B. table method
C. Comparative method
D. Difference method
Answer: B
Analysis: Among the methods of cost control for construction projects, different methods can be used for deviation analysis, and common methods are cross-path diagram method, curve method and table method.
6. A project contains two sub-items A and B. The contract stipulates that the comprehensive unit price of item A is 200 yuan/㎡, and the comprehensive unit price of item B is 180 yuan/㎡; the progress is calculated monthly, and the actual completion of item A in the first month is 700㎡, and the project payment that should be paid this month is () million yuan.
A.20
B.23
C.25
D.30
Answer: B
Analysis: Two sub-item projects of A and B, the contract stipulates that the comprehensive unit price of item A is 200 yuan/㎡, and the comprehensive unit price of item B is 180 yuan/㎡; the progress is calculated monthly, and the actual completion of item A in the first month is 700㎡, and the project payment that should be paid this month is 230,000 yuan.
7. The basis for construction cost control does not include ().
A. Project contract
B. Progress report
C. Construction drawing
D. Construction cost plan
Answer: C
Analysis: The basis for construction cost control: ① Project contract; ② Construction cost plan; ③ Progress report; ④ Project changes.
8. Project cost control does not include ().
A.Measure fee control
B. Material fee control
C. Labor fee control
D. Management fee control
Answer: A
Analysis: Engineering project cost control is mainly controlled from four aspects: ① Control of material fee; ② Control of labor fee; ③ Control of machinery fee; ④ Control of management fee.
9. A foundation project contains two sub-items, earth and concrete. The earth and stone project volume in the bill of quantities is 4400 cubic meters, and the concrete project volume is 2000m³. The contract stipulates that the comprehensive unit price of earth and stone project is 75 yuan/, and the comprehensive unit price of concrete project is 420 yuan/m³; the project advance payment amount is 15% of the contract price. Then the prepayment amount for the project is () million yuan.
A.14.55
B.17.55
C.20.55
D.24.7
Answer: B
Analysis: A foundation project contains two sub-items of earth and stone and concrete. The earth and stone project volume in the bill of quantity is 4400 cubic meters, and the concrete project volume is 2000m³. The contract stipulates that the comprehensive unit price of earth and stone project is 75 yuan/m³, and the comprehensive unit price of concrete project is 420 yuan/m³; the project prepayment amount is 15% of the contract price. The prepayment amount for the project is 175,500 yuan.