22 first-class cost engineer case test point supply of materials and engineering equipment, cost engineer academic master notes, long press and like + forward + evaluation continue to be updated, click on my avatar on the Wendang version and send a private message to me: 2022
(1) Acceptance of the materials and engineering equipment supplied by the contractor.
For the materials and engineering equipment provided by the contractor, the contractor shall conduct inspection and delivery acceptance with the supervisor, check the material qualification certificate and product qualification certificate, and conduct sampling inspection and engineering equipment in accordance with the contract agreement and the supervisor's instructions. The inspection, inspection and test results of the inspection and test shall be submitted to the supervisor, and the required costs shall be borne by the contractor.
(2) Acceptance of materials and engineering equipment supplied by the contractor.
The contractor shall notify the contractor 7 days before the arrival of the materials and engineering equipment, and the contractor shall, together with the supervisor, go to the delivery location for acceptance together within the agreed time.
Unless otherwise agreed in the terms of the special contract, the contractor shall be responsible for receiving, transporting and storing the materials and engineering equipment provided by the contractor after acceptance. If the specifications, quantity or quality of the materials and engineering equipment provided by the contractor does not meet the contract requirements, or if the delivery date is delayed and the delivery location changes are caused due to the contractor, the contractor shall bear the increased costs and (or ) The construction period is delayed and reasonable profits are paid to the contractor.