Minhou Erqiao Sugarcane Interconnection renderings.
Fuzhou News Network, June 6 (Fuzhou Daily reporter Xie Xingxing, correspondent Zhang Cunjin, Chen Jiansheng) The reporter learned on the 6th that as an important area for cross-river development of the large county in Minhou, the construction project of Zhuqi New District has blossomed at multiple points. Among them, many projects such as Minyue Water Town, Minjiang South Bank flood control phase 6, river channel improvement in Maipu area, and road network in the new district are all under construction.
flood control phase six project and Jiangbin Road combined with simultaneous construction
html On the morning of the 16th, the reporter came to the Minyue Water Town project site and saw that the core area of the project is being fully constructed, the facade decoration construction of the city gate building has been basically completed, and 80% of the construction of the North and South Square has been completed. The interior decoration of the tourist reception center is underway, and the street trial business will be opened as soon as next year.Around Minyue Water Town Project is distributed with many important roads in the new district road network. What is under construction along the Minjiang section is the sixth phase of flood control project on the south bank of the lower reaches of the Minjiang River and Jiangbin Road in Zhuqi New District. "These two projects are constructed simultaneously by combining embankments and roads." Lu Bizhu, senior engineer of Minhou County Water Conservancy Bureau, introduced.
Among them, the sixth phase of flood control project will be newly built and reinforced with 7.6 kilometers of flood control embankment in the Zhuqi section of Minjiang River, as well as 2 pump stations and 5 sluice gates. The standard for preventing floods in the Minjiang River adopts the standard for preventing floods in the Minjiang River adopts the standard for preventing mountain torrents and drainage. "The original flood control embankment has been disrepair for many safety hazards. This time, the flood control embankment will be raised and broadened to comprehensively improve flood control capabilities." Lu Bizhu said that the project is constructed in sections, and the C6 section is currently under construction. It is expected that the earth filling and shore wall construction of the embankment will be completed by the end of June next year, and the hydrophilic platform hardening and ecological slope protection construction will be completed. The entire C6 section is strived to be completed by the end of August next year.
Zhuqi New District Jiangbin Road is lined along the flood control embankment, and is built using the standard of urban secondary trunk roads. The road is 30 meters wide, 4 lanes in both directions, and a designed speed of 40 kilometers per hour. "Like the flood control embankment, Jiangbin Road is also constructed in sections, and the second section is currently underway." The project construction party introduced that it is striving to complete the roadbed filling and pipeline burial by the end of August next year, and to complete the construction of the second section by the end of August next year.
3 roads will be built within the year
around Minyue Water Town. In addition to Jiangbin Road, road projects such as Zhuqi New District No. 1, No. 2, and No. 3 are being built. These roads are the "lifeline" connecting the outside of Zhuqi New District.
Outside the city gate tower of Minyue Shui Town, the reporter saw that Road No. 1, which is about 300 meters long, has a rough scale. "Road 1 connects 316 National Highway and 3, and is expected to be completed in September." said a relevant person in charge of the Minhou County Transportation Bureau.
Road 2 is about 1.4 kilometers long. It starts from the starting point and connects National Highway 316. After leveling with Road 3, it continues to go north and the end point is Jiangbin Road. The 3.4-kilometer-long Road No. 3 is built around Minyue Water Town. It starts from Jiangbin Road (near the side of Minhou Bridge), intersects with Road No. 1 and Road No. 2 along the line, and ends with Jiangbin Road (near the side of Bailongzhou Bridge).
"Road 2 and Road 3 are also under construction in full swing, striving to complete the construction within the year." The above-mentioned person in charge said that after Road 1, 2 and 3 are opened to traffic, the road network of Zhuqi New District will be fully revitalized.
Minhou Second Bridge is expected to be designed this month
as the connection channel between Zhuqi New District and the county town, and the Minhou Second Bridge project has attracted much attention from citizens. The reporter learned on the 6th that the project has completed the preliminary design of the main bridge part and the design of the road wiring part is being improved. The overall design is expected to be completed this month and bidding will be launched in September.
"The project route starts from National Highway 316, and the main bridge spans the Minjiang River, and the end ends at Sugarcane Bincheng Avenue. It is set up to connect the North Bank Interchange with North Binjiang Road, and the south bank Interchange is reserved to connect to Jiangbin Road in Zhuqi New District." A relevant person in charge of the Minhou County Transportation Bureau said that the Minhou Second Bridge is a cross-river channel connecting Zhuqi, sugarcane and Jingxi. The project construction will further strengthen the convenient connection between Zhuqi and Fuzhou central urban area, providing good basic conditions for the cross-river integration development of Minhou urbanization.