is a variety of temporary buildings, temporary facilities and materials, and construction machinery arranged as construction services on the building plane of the proposed project. It is the space for construction plans in the site. It reflects the interrelationship between the existing buildings and the intended engineering, temporary buildings and temporary facilities. Whether the layout is appropriate or not, the implementation of the implementation, the construction organization, the construction of civilization, and the construction progress, the cost of engineering , engineering quality and security will have a direct impact. Therefore, the plane layout of the construction site must be arranged reasonably and scientifically.
Construction Total Plane Design Points
construction site The door. The gate should consider the surrounding road network conditions, turning radius and slope restrictions. The height and width of the gate should meet the needs of vehicle transportation. As much as possible, consider the effective connection with the location of the processing site and warehouse. There should be dedicated personnel in and out of the passage and management auxiliary measures.
02
— Set up large -scale mechanical equipment -
to arrange tower cranes, the weight of its coverage, the weight of the hangable components, and the transportation and stacking of components should be considered. When the position of the concrete pump is arranged, the conveying distance of the pump tube should be considered and the concrete tank truck is convenient. Generally, the tube should be relatively fixed, and the pump truck can be used on the spot. When arranging the construction lifting machine, the base bearing capacity, the flatness of the foundation, the drainage of the surrounding area, the attached wall position and distance of the rail frame, the floor platform channel, the protection door of the entrance and exit, and the protective fence around the lifting machine.
03
— Putting warehouses, stacking —
should generally be close to the location, and its vertical should be parallel to the traffic line. The on -site facilities should be unloaded as much as possible. The warehouse that stores the dangerous category should be set up separately from the scene, and the distance from the construction project should not be less than 15m.
04
— The general guidance idea of
is to minimize the amount of transportation of materials and components, and vertical transportation equipment to play a large role; related processing plants properly concentrated.
05
— Temporary transportation roads in the layout —
main roads shall be hardened, and the main roads should have drainage measures. Temporary roads should penetrate warehouses, processing plants, yards and construction points, and design double -line trunk roads or single -line loop channels according to the size of the freight volume to meet the transportation and fire requirements. The width of the main road is not less than 4m, and the double -line road is not less than 6M. There should be 6m wide channels on both sides of the wood farm, and the end of the end should be , 12m × 12M. The fire lane should not be less than 4m. It is handled according to the actual situation and meets the fire protection requirements when the on -site conditions are not met.
06
— Temporary House -
(1) Try to use the built -of -built permanent houses as construction services, and temporary houses are constructed. Temporary houses should try to use the demolished activity house and meet the fire protection requirements. If possible, the living areas, office areas and construction areas should be relatively independent. The dormitory should ensure the necessary living space. The net height of the room shall not be less than 2.5m, the width of the channel shall not be less than 0.9m, and each dormitory shall not exceed 16.
(2) office rooms should be located at the entrance of the site.
(3) The dormitory of operators should be set up near the scene to facilitate workers to get off work; when conditions permit, they can also be located in the field area. The living welfare facilities used by operators should be set up in a relatively concentrated place, or they must be located where they go.
(4) The cafeteria should be arranged in the living area, and it can also be located between the construction area and the living area. If on -site conditions are not allowed, the meal delivery system can also be used.
07
— Arrangement of temporary water, electric pipe network and other power facilities -
temporary total transformer station should be set at the entrance of the high -voltage line to avoid crossing the construction site as much as possible.
introduces water into the construction site from the municipal water supply connection point.The pipe network is generally arranged along the road. The power supply line should be avoided as other pipelines on the same side. At the same time, the branches should be led to all electric equipment use locations. The organization facilities shall be organized in accordance with the approval of the "XX Project Temporary Water and Electricity Construction Technology Plan".
construction total plane map shall be drawn in accordance with the drawing rules, proportion, specified code, and specified lines, and classify the design of the design on the graph, indicate the name, legends, ratio, direction mark, and necessary text description.