Polaris Atmosphere News: 1. Project name: Shandong Sunshine Power Co., Ltd.’s new 30MW biomass cogeneration project

Project overview: Shandong Sunshine Power Co., Ltd. The new 30MW biomass cogeneration project is located in Laiwu, Jinan City District Niuquan Town is planned to be built in the factory area of ​​Shandong Sunshine Power Co., Ltd. to the north of the first road and east of the west outer ring road, using the development land reserved by the company. The

project mainly includes: a new 1×130t/h biomass-fired high-temperature and high-pressure circulating fluidized bed boiler + 1×30MW extraction condensing steam turbine generator unit, supporting the construction of a boiler room, turbine room, deaeration room, and semi-enclosed Storage warehouse, circulating slurry pump room, circulating water pump room, ash warehouse, desulfurization wastewater and concentrated brine treatment station, boiler flue gas purification system, flue gas online monitoring system, accident water Boxes and other facilities; water supply pipe network (the water source is water from Laixin Iron Mine), counterflow hyperbolic natural ventilation cooling tower, slag storage room, desulfurization gypsum temporary storage room, lime powder warehouse, domestic sewage treatment station, chimney, ammonia storage Tanks, hazardous waste temporary storage rooms, accident pools, first heating stations, office and living facilities are based on the company's existing projects; the total investment in the

project is 171.34 million yuan, of which 21.8 million yuan is invested in environmental protection. Ten thousand yuan, electricity is determined by heat. The annual utilization hours of the boiler and unit are 8000h, the power supply is 1.775×108kWh/a, and the heat supply is 7.81×105GJ/a. After completion, it is planned to provide production use to 4 companies in Niuquan Town, Laiwu District. Steam and 6 domestic heating users.

2. Contact information

Construction unit: Shandong Sunshine Power Co., Ltd.

  • Contact person: Mr. xx

  • Telephone: 0634-xxx240

  • Fax: 0634-xxx222

  • Address: Laiwu City, Shandong Province xxxx

Address: Laiwu City, Shandong Province, China xxxx

1. Basic situation of the project Project name: Boli County Biomass Cogeneration Project

Construction nature: New construction

Construction location: In the west area of ​​Boli Industrial Park, Boli County

Construction unit: Boli Kairun New Energy Technology Co., Ltd.

Construction content: Planned Build a 13130t/h high temperature and high pressure circulating fluidized bed biomass boiler, equipped with a 1330MW extraction condensing steam turbine and a 1330MW generator set. The annual utilization hours of boiler equipment are calculated as 7200h, the annual utilization hours of power generation equipment are calculated as 7200h, the annual heat supply is 82.33104GJ, the heating heat load heat supply is 16.3316 3104GJ, and the industrial heat load annual heat supply is 65.96843104GJ. The annual power generation is 2.163108 kWh. The power supply is 1.81663108 kWh, and the annual biomass consumption is 2.439043105 t.

Labor capacity and work system: The factory has a capacity of 139 people, 120 production personnel, and the actual production days per year are 300 days. It adopts a three-shift system, with each shift of 8 hours. Total investment and environmental protection investment of

project: The total project investment is 296.1247 million yuan, and the environmental protection investment is 29.45 million yuan. Environmental protection investment accounts for 9.94% of the total investment.

Surrounding situation: This project is located in the west area of ​​Boli Industrial Park, Boli County, Qitaihe City. The west side of the factory area is the logistics park, the east side is farmland, and the north and south sides are planned construction lands. The total land area of ​​the factory area is 60,000m2. The construction area is 14684m2.

2. Contact information

Construction unit: Boli Kairun New Energy Technology Co., Ltd.

Legal representative: Zhang Chi

Contact person: Cang Xiaodong

Correspondence address: No. 338 Youyi East Street, Boli County (Room 431, Area B, Government Office Center )

Contact number: 18640068371

Fax/Postal code 154500

construction site West District of Boli Industrial Park, Boli County, Qitaihe City, Heilongjiang Province

1, basic project information

Project name: Bin County Changqing Biomass Cogeneration Project

Construction nature: New construction

Construction location: Bin County, Harbin City Bin West Town West side of Sujiatun

Construction unit: Binxian Changqing Biomass Energy Co., Ltd.

Construction content: Planned to build 1×35MW Extraction-condensing steam turbine generator unit, equipped with a 140t/h high-temperature and high-pressure water-cooled vibrating grate biomass boiler.The annual utilization hours of boiler equipment are calculated as 8181h, the annual utilization hours of power generation equipment are calculated as 6100h, the annual power supply is 2.135×108kWh, the central heating capacity is 30MW, the industrial steam heating capacity is 44t/h, and the annual fuel consumption is Substance 31.75×10 4 t. Total investment and environmental protection investment of

project: total project investment is 426.58 million yuan, and environmental protection investment is 11.755 million yuan. Environmental protection investment accounts for 2.76% of the total investment.

Surrounding situation: The construction site of this project is located in Binxi Town, Bin County, Harbin City. The south side of the project is Linhai Xueyuan Pharmaceutical Co., Ltd., the north side is woodland, the west side is separated by the Fiketu River, and the east side is separated by cultivated land. Tun.

2. Contact information

Construction unit: Binxian Changqing Biomass Energy Co., Ltd.

Supervisor: You Jie

Contact number: 13039983408

1. Project name and summary

1. Project name: Hongdong County People's Livelihood Waste Comprehensive Treatment Company newly built Hongtong County Domestic Waste Harmless Treatment and Power Generation Project

2. Construction unit: Hongdong County People's Livelihood Waste Comprehensive Treatment Company

3. Construction nature: New construction

4. Construction location: Hongdong It is 700m north of Guxian Village, Subao Town, County.

5. Total investment: 321.0445 million yuan.

6. Construction content: This project has a daily processing capacity of 600 tons of domestic waste. It is equipped with four pyrolysis incinerators with a processing capacity of 150t/d. It adopts medium temperature and medium pressure (400℃, 4.0MPa) waste heat boiler , and is equipped with one 12MW waste heat boiler. The pure condensing steam turbine generator unit can incinerate 235,000 tons of garbage annually and generate 75.95 million kWh of electricity annually. At the same time, supporting construction of fly ash stabilization treatment project and flue gas purification treatment facilities will be completed.

2. Contact information of the construction unit

Name of the construction unit: Hongdong County Minsheng Waste Comprehensive Treatment Company

Address of the construction unit: 700m north of Guxian Village, Hongdong County

Contact person and contact information: Mr. Guo, 17635284555

Email Box: [email protected]

1. Project name and project summary

Project name: Shaoyang City Xinshao Waste incineration power generation project

Project location: Xinshao County Tangkou Village, Xintianpu Town (Tangkou Industrial Park ). The site is located on the north side of Tangkou Village, northwest of Xinshao County. The straight-line distance from the county center is about 6.7km, and the transportation distance is about 8km. On the north side is about 310m Zishui River, and on the south side is about 900m Xinshao Avenue. .

Processing scale: The recent phase of the Xinshao domestic waste incineration power plant project in Shaoyang City has a daily waste processing capacity of 1,000t/d and an annual processing capacity of 365,000t.

Main construction content: The project plans to build two 500t/d mechanical grate furnaces, two 42.4t/h medium-temperature and sub-high-pressure (6.4MPa, 450℃) waste heat boilers, and one 25MW turbine generator, with annual power generation The capacity is about 127.75 million kW·h. The main construction contents include: 2×500t/d garbage incinerator and supporting waste heat boiler; garbage transportation and unloading hall and garbage storage pit; garbage incinerator loading system; slag removal and ash removal system; flue gas purification system; water supply system ; Turbine generator set and steam supply and condensation system; central control and monitoring system; physical and chemical analysis room, chemical water treatment room; duty room, conference room; air compressor room; machine repair, warehouse, etc.

2. Contact information

Construction unit: Xinshao County Urban Management and Comprehensive Law Enforcement Bureau

Contact person: Zhou Jinming Contact number: 15973988978

1. Planning name and summary

Planning name: Jingzhou Central City Combined Heat and Power Planning (2019 ~2030).

Summary: In order to meet the heat load demand in Jingzhou's central urban area and guide the orderly development of the district heating industry, the Jingzhou Municipal Development and Reform Commission commissioned the preparation of the "Jingzhou Central Urban Area Cogeneration Plan (2019~2030)". The plan divides the central urban area of ​​Jingzhou into two heating areas: eastern and western. The eastern heating area includes the central area, Jingzhou Development Zone, and Guanju area; the western heating area includes Paima Industrial Park, Lingang Industrial New City, Chengnan area, Jingbei - Yingcheng area, the core area of ​​Jingzhou High-tech Zone and the ancient city area, the heat load in the above areas uses the method of combined heat and power for centralized heating.

2. Planning unit name and contact information

Unit name: Jingzhou Municipal Development and Reform Commission

Contact address: No. 54, Jingzhou East Road, Postal Code: 434000

Contact person: Xue Wenyi

Contact number: 0716-8453290 Contact fax: 0716-8457604

Email: [email protected]

1. Construction project name, site and line selection, construction content and other basic information:

Project name: Angel Yeast ( Ili River ) Co., Ltd. 6MW back-pressure cogeneration project;

Construction unit: Angel Yeast (Ili River) Co., Ltd.;

Project location: The project is located at Horgos Port h of the XPCC tml6 Industrial Park Area B, Area 2 East Area (within Angel Yeast (Ili River) Co., Ltd.);

Construction project overview: This project is a new project, and it is planned to build a 3×65T/h medium temperature and medium pressure circulating fluidized bed steam boiler (Dual-purpose and one standby) and 6MW back-pressure turbine generator Set 1 set, which is a supporting project of the 32,000-ton yeast products green manufacturing project of Angel Yeast (Ili River) Co., Ltd. It uses waste heat and pressure to generate electricity to generate 6MW of electricity per hour. After being connected to the grid, it can be used by Angel Yeast (Ili River) Co., Ltd. will eventually be built to supply steam up to 130T/h with a pressure of 0.8MPa. The total investment in the construction of the

project is 106 million yuan, including 98 million yuan in fixed asset investment and 8 million yuan in working capital.

Construction project name, site and line selection, construction content and other basic information:

Project name: Keke Dala Angel Yeast Co., Ltd. 3×65T/h coal-fired boiler heating project;

Construction unit: Keke Dalaan Qi Yeast Co., Ltd.;

project location: The project is located in Horgos Port Industrial Park B, Xinjiang Corps In the middle area of ​​District 2 (Central District 2, West District, Kekedala City Industrial Park) Angel Yeast Company;

construction project overview: This project is a new project, and it is planned to build a 3×65T/h medium temperature and medium pressure circulating fluidized bed The steam boiler (dual use and one standby) is a supporting project of the 32,000-ton yeast product green manufacturing project of Kekedala Angel Yeast Co., Ltd. It will eventually be built to supply steam with a capacity of 130T/h and a pressure of 0.8MPa. The total investment in the construction of the

project is 106 million yuan, including 98 million yuan in fixed asset investment and 8 million yuan in working capital.

2. Construction unit and contact information

Unit name: Angel Yeast (Ili River) Co., Ltd.

Address: No. 4199, Chongqing Road, Economic Cooperation Zone, Yili Development Zone, Xinjiang

Contact person: Zhang Jie

Telephone: 18999584265

1. Project Overview

Project Name: Sewage treatment plant and supporting pipe network construction project

Construction nature: Newly built

Total investment: 60 million yuan

Construction location: Sanlong Town Industrial Park, Dafeng District, Yancheng City

Construction content: It is planned to invest 60 million yuan to build a new urban industrial sewage treatment plant. The planned total treatment scale of the sewage treatment plant 20,000 cubic meters per day, which will be constructed in two phases. The first phase has a construction scale of 10,000 cubic meters per day, and the second phase has a construction scale of 10,000 cubic meters per day. It will be equipped with a dedicated industrial sewage transportation pipeline network of about 25 kilometers.

2. Contact information

Name of the construction unit: Jiangsu Shuifa Huaxia Environmental Technology Co., Ltd.

Contact person: Mr. Wang

Contact number: 18905111278

Mailing address: Sanlong Town Industrial Park, Dafeng District, Yancheng City

Email: [email protected]

Original title: Project collection: biomass thermoelectricity, solid waste treatment, waste power generation , combined heat and power, central heating, sewage treatment

Disclaimer: The above content is reproduced from Polaris Atmosphere Network, all The content posted does not represent the position of this platform.