Question 1: What should we pay attention to when installing valves? Question 2: What matters should be paid attention to when installing the compensator? Question 1: What should we pay attention to when installing valves? Reference: (1) Appearance inspection should be carried out

2024/06/1909:44:32 home 1633

question 1. What should we pay attention to when installing valves?

Question 2. What should you pay attention to when installing compensator ?

Question 1: What should we pay attention to when installing valves? Question 2: What matters should be paid attention to when installing the compensator? Question 1: What should we pay attention to when installing valves? Reference: (1) Appearance inspection should be carried out - DayDayNews


Question 1. What should we pay attention to when installing the valve? Reference:

(1) Appearance inspection should be carried out before the valve is installed. Valves and check valves whose working pressure is greater than 0.1MPa and which have the function of cutting off the main pipeline and regulating the system's cold and hot water operation conversion and should be inspected. Strength and valve disc sealing performance testing, and the test should be qualified. The strength test pressure should be 1.5 times the nominal pressure under normal temperature conditions, and the duration should not be less than 5 minutes. The valve shell and packing should be free of leakage. The tightness test pressure should be 1.1 times the engineering pressure, and the pressure should remain unchanged during the test duration.

(2) The handle of the manual valve installed on the insulated pipe must not face downwards.

(3) The actuator of electric valve should be able to control the opening and closing of the valve throughout the process.

Question 2: What matters should be paid attention to when installing the compensator? Reference:

(1) The compensation amount and installation position of the compensator should comply with the requirements of the design document, and should be pre-stretched or pre-compressed according to the calculated compensation amount in the design.

(2) Regardless of the welded side of the expansion joint or compensator, the horizontal pipeline should be installed at the inflow end of the water flow, and the vertical pipeline should be installed at the upper end.