The content of the second-level construction engineer management gold test site progress payment application form in 2023, the second-level construction master notes, long press and like + forward + comments to continue to be updated, click on my avatar on the Wendang version to

2023 second-level construction engineer management gold test site progress payment application form, second-level construction academic master notes, long press and like + forward + evaluation continue to be updated, Wendang version click on my avatar and send a private message to me: 2022

(1) The amount corresponding to the work completed as of this payment cycle;

(2) The amount of change that should be increased and deducted according to the "change";

(3) The prepayment that should be paid and the deducted return of the deducted according to the "advance payment" agreement;

(4) The quality deposit that should be deducted according to the " quality deposit " agreement;

(5) The amount of claim that should be increased and deducted by "claim";

(6) If an error occurs in the issued progress payment certificate, the amount that should be paid or deducted in this progress payment;

(7) Other amounts that should be increased and deducted according to the contract agreement

. Progress payment review and payment

(1) The supervisor shall complete the review and submit it to the contractor within 7 days after receiving the contract payment application form and the relevant

information. The contractor shall complete the approval and issue the progress payment payment certificate within 7 days after receiving the contractor's progress payment application form and the relevant

information. If the contractor fails to complete the approval within the deadline and does not raise any objection, it shall be deemed that the progress payment payment certificate has been issued;

(2) The contractor shall pay the progress payment to the contractor within 14 days after issuing the payment certificate;

(3) The contractor issues the progress payment payment certificate or the temporary progress payment payment certificate, which does not indicate that the contractor has agreed, approved or accepted the corresponding part of the work completed by the contractor.