Drive south from the Yatai Street Elevator, a magnificent and tall antique building comes into view, resembles the landmark building of Changchun Cultural Square - Jilin University Geology Museum. This is the new expressway toll gate after the exit of the Fuchang Expressway Peopl

Fuchang Expressway People's Street Exit Reform Project

will be officially opened to traffic at 24:00 on October 13

Drive south from the Yatai Street viaduct, a magnificent and tall antique building comes into view, which is similar to Changchun Cultural Square - Jilin University Geological Museum . This is the new highway toll gate after the exit of Fuchang Expressway People's Street was relocated.

1:00 on October 13, this gate will be officially opened, marking the official opening of the new Fuchang Expressway South Exit. At the same time, the Changchun South Toll Station on Jinyu Road will be stopped and the lane will be closed.

Urban Evening News All-Media Reporter photographed one after another

Fuchang Expressway People's Street Exit Reform Project Designed a total length of 12.623 kilometers, covering an area of ​​169 hectares. The starting point of the line is located on the north side of the natural village, connecting to the current Fuchang Expressway . Along the line, passing through Chaoyang District , Nanguan District , and Jingyue District, the end point is located on the south side of Changchun South Fourth Ring Road, and connected to the current Yatai Street extension line.

project adopts a two-way eight-lane expressway standard with a design speed of 120km/h, with a roadbed width of 42m, and a bridge design load level of highway-I. There is 1 channel, 2 culverts, 2 interchangeable three-dimensional intersections, 2 toll stations, and 1 maintenance work area (constructed with toll stations). After the completion of the project, the service level of Fuchang Expressway can be effectively improved, the central axis function of Renmin Street urban, the layout of the urban road network can be improved, and the space for urban development can be further alleviated.

The overall construction period of the Fuchang project is 3 years (September 2020-October 2022) and started construction in September 2020. The project lasted 25 months. During this period, due to winter maintenance, epidemics, large rainfall, etc., the actual construction period can be 15 months. After the unremitting efforts of all participating units and builders, at the end of September 2022, the Fuchang project completed the construction task one month ahead of schedule. Currently, Jigao Group is organizing acceptance and plans to officially open transportation at 24:00 on October 13.

It is understood that in order to effectively promote the comprehensive traffic management work in Changchun City, Changchun City has formulated and implemented a policy of free point-to-point traffic between 10 toll stations of the Ring Expressway using the Ring Expressway to divert urban vehicles and Ji A licensed vehicles, effectively alleviating the urban traffic congestion pressure caused by the maintenance and reinforcement of the South Fourth Ring Cross-Yitong River Bridge and other projects. However, it is estimated that after the opening of the newly built Fuchang Expressway entrance and exit (New Changchun South Entrance and Exit), the traffic volume growth trend in surrounding areas such as Yatai Street and South Fourth Ring Road has been obvious, and the road traffic pressure is relatively high. In order to alleviate the impact of the new Changchun South entrance and exit on surrounding traffic after the opening of traffic and ensure smooth roads, the Changchun Municipal Traffic Management Committee has decided that the new Fuchang Expressway entrance and exit (New Changchun South Entrance and Exit) is not within the scope of the Changchun Ring Expressway point-to-point free passage policy. Passengers must pay normally according to the relevant toll standards of the expressway.

, Director of the Operation Department of Jigao Group, said that at 24:00 on the 13th, the Changchun South Toll Station on Jinyu Road will be stopped and the lane will be closed. At the same time, the New Changchun South Toll Station on Yatai Street will be opened on time. For this reason, they have formulated a detailed switching plan and carried out multiple drills to ensure smooth and orderly switching under the continuous flow of the main line. 18 vehicles will be used to ensure the on-site switching, and 76 staff members will participate in the on-site switching, achieving seamless connection between the start and stop of the new and old toll stations, and the rapid switching between new and old road sections. html vehicles that plan to enter the expressway through the Changchun South Toll Station after 24:00 on the 113th, please choose the Changchun South Toll Station of Yatai Street to pass. Vehicles who drive out of the new Changchun South Toll Station can directly pass through the Yatai Street Expressway and enter the urban area. New Changchun South Toll Station has 28 lanes with 9 entry and 19 exit, with a traffic capacity of nearly twice that of the original Changchun South Toll Station. The debugging of all lanes has been completed.

Source: City Evening News All Media Reporter

Editor: Zhao Mingming