On March 8, a reporter from Upstream News learned from Chongqing Transportation Investment Group that the construction of 7 projects, including the first phase of the urban rail express line 15, the second phase of the 15, the second phase of the 27th phase of the urban rail express line, the river jumper line of the city (suburban) railway, the first phase of the 1st line of the 1st line of the 1st line of the 1st line of the 1st line of the 1st line of the 1st line of the 1st line of the 1st line of the 1st line of the 1st line of the 1st line of the 1st line of the 1st line of the 1st line of the 1st line of the 1st line of the 1st line of the 1st line of the 1st line of the 1st line of the 1st line of the 1st line of the 1st line of the 1st line of the 1st line of the 1st line of the 1st line of the 1st line of the 1st line of the 1st line of the 1st line of the 1st line of the 1st line of the 1st line of the 1st line of the 1st line of the 1st line of the 1st line of the 1st line of the 1st line of the 1st line of the 1st line of the 1st line of the 1st line of the 1st line of the 1st line of the 1st line of the 1st line of the 1st line of the 1st line of the 1st line of the 1st line of the 1st line of the 1st line of the 1st line of the 1st line of the 1st line of the 1st line of the 1st line of the 1st line of the 1st line of the 1st line of the 1st line of the 1st line of the 1st line of the 1st line of the 1st line of the 1st line
———
Urban Rail Express Line 15 Phase I:
fully enters the construction stage of the main project

15 Phase I direction diagram
Urban Rail Express Line 15 Phase I project is about 38.7km long, starting from Jiuqu Hedong Station, and finally at Liangjiang Film and Television City Station, with 14 stations (Jiuqu Hedong Station, Chongqing Guang Station, Long'an Road Station, Jintong Road Station, Guotang Road Station, Southwest University of Political Science and Law Station, Baosheng Lake Station, Xiuhu Road Station, T3 Terminal Station, Longjun Avenue Station, Liangjiang Avenue Station, Fusheng Station, Modern Avenue Station, Liangjiang Film and Television City Station).

15 Line 015 Construction channel of Jiuquhedong Station Open Tank Section
As of now, there are 35 working points in the first phase of Line 15, and each section has fully entered the main project construction stage. The first composite TBM has been removed from the line, and the control projects of nodes such as the Tongluoshan Tunnel are being promoted normally.
———
Urban Rail Express Line 15 Phase II: The construction of
7 construction sites has entered the site. The direction diagram of the second phase of

15
15
15 Phase II project is about 32.8km long, starting from Zengjia Station in the west and ending at Jiuquhe East Station in the east (excluding) with 11 stations (Zengjia Station, University Town Middle Road Station, University Town South Station, Chenjiaqiao Station, University Town North 1 Road Station, Zhangjiawan Station, Logistics Yuan North Station, Jingkou Station, Lixue Road Station, Jinshan Temple Station, Happy Valley Station).

15 Phase II Zhongliangshan Tunnel Construction Site
As of now, 7 construction sites of Phase II of Line 15 have entered the site (Zengjia Station, University City South Station, Zhongliangshan Tunnel Imported and Drainage and Construction Channel, Liaojiaxi Bridge East and West Bridgetou, Lixue Road Station, and Happy Valley Station Construction Channel). We are accelerating the construction of temporary construction and traffic guidance reform. The construction channel of the Zhongliangshan Tunnel, the Liaojiaxi Bridge and Happy Valley construction channel are being carried out at a rapid pace.
———
Urban Rail Express Line 27:
Three major node control projects have all entered the site and started construction

27 Line direction diagram
Urban Rail Express Line 27 is about 51.9km in total, starting from Bishan Station in the west and ending at Chongqing East Station in the east , with 14 stations [Bishan Station (construction agency), Huxi Station, University City South Station, Zhaishanping Station, Xiyong Station , Ciqikou Station, Shapingba Station , Shiqiaopu Station , Daping West Station, Chongqing Station (construction agency), Houbao Station, Nanping Station, Guangfu Avenue Station, and Chongqing East Station (construction agency)], with 1 Bishan parking lot, 1 Chongqing East Depot, and 3 main substations.

27 Tongluoshan Tunnel Construction Site
As of now, 17 Line 27 have entered the site (Bihu Elevated Zone, Jinyunshan Tunnel Import, University City South Station, Zhaishanping Station, Zhongliangshan Tunnel Import, Ciqikou Station Transfer Hall, Ciqi Station Construction Channel, Cisha Zone Construction Channel, Shapingba Station Construction Channel, Shiqiaopu Station Construction Channel, Daping West Station Construction Channel, Houbao Station Construction Channel, Nanping Station Construction Channel, Tongluoshan Tunnel 1# Construction Channel, Tongluoshan Tunnel 2# Construction Channel, Tongluoshan Tunnel 2# Wind Well, Guangfu Avenue Station). The three major node control projects of the entire line, Jinyunshan Tunnel, Zhongliangshan Tunnel, and Tongluoshan Tunnel have all started construction, and the 11 civil engineering section project stations have been completed and put into use.
———
suburban railway river jumper
Jiangjin District Domestic vehicles have been launched joint debugging and testing

river jumper direction diagram
suburban railway river jumper lever is about 28 kilometers long, starting from the jujube station on rail transit Line 5, and ending at Jiangjin Shengquan Temple Station. There are 6 stations on the entire line (Shilin Temple Station, Jiulongyuan Station, Shuangfu Station, Xiangtang Station, Jiangjin High-speed Railway Station, Shengquan Temple Station), and a Shuangfu Depot is set.

Jiang Jumper Line Jiulongyuan Station Construction Site Lei Jian Photo
As of now, the entire line of civil engineering has been basically completed.The "long rail connection" of the entire line was completed in January, and the "power connection" of the entire line was achieved on March 5, and the acceptance and handover work is being accelerated. 15 vehicles have been assembled, and vehicle acceptance and debugging work has been continuously promoted; vehicles in Jiangjin District have been launched and jointly debugged and tested, and are accelerating the decoration and installation and debugging work of the entire line.
———
Suburban Railway Bigong Line:
comprehensively carry out interval bridge construction and construction

Bigong Line direction diagram
Bigong Line is about 37.4 kilometers long, and there are 9 stations (Bishan Station, Daishan Avenue Station, Hebian Station, Qinglong Lake Station, Dalu Station, Pulu Station, Tongliang New City Station, Tongliang Station, and Tongliang West Station).

Bi Tong Line Yunwushan Tunnel Construction Site
As of now, the copper beam station pile foundation has been completed by 100%, and the construction of the bearing and pier columns is being accelerated; the construction of interval bridges has been fully carried out, and civil engineering projects have been completed by 93%. All 8 construction branches of the Bitong Line have entered the site, of which 335 pile foundations have been completed in the bridge project, 31 support platforms have been completed, 24 pier columns have been cast, and 2 box beams have been cast in total. Yunwushan Tunnel main hole has a cumulative footprint of 954m, a cumulative footprint of 312m, and a cumulative footprint of 533.9m.
———
Suburban Railway Chongqing Hebei Line Phase I:
Civil engineering project has completed 85% of the total

Chongqing Hebei Line Phase I direction diagram
Chongqing Hebei Line Phase I project is about 8 kilometers long, of which about 6 kilometers of Xiangyu left line is changed and about 2 kilometers of Moxinpo North Field.

The construction site of the first phase of the Chongqing He Line, the construction site of the double-land bridge of the first phase of the Chongqing He Line, has completed 85% of the civil engineering projects, and the construction of the superstructure and roadbed of the bridge is being accelerated, and the construction procedures of existing lines have been basically completed.
———
Guanba Railway Special Line:
Accelerate the construction of Fuba Station and overturner foundation pit
Guanba Railway Special Line is about 13.4 kilometers long and has 2 stations (Kanshui North Connection Station and Fuba Station).

Guanba Railway Special Line Fuba Station Construction Site
As of now, the offline civil engineering project has been basically completed except for Fuba Station, and the construction of Fuba Station and the overturning machine foundation pit is being accelerated. The rail project has completed the procurement of materials, and the Si Electrical Engineering is conducting bidding for materials and equipment.
Source: Upstream News Reporter Wang Zihan