Notice on the traffic control during the cleaning construction of the Strait Convention and Exhibition Center on Nanjiang Binxi Avenue
Underpassing the roadway, etc.
Traffic control during cleaning construction
After application by the Municipal Environmental Sanitation Center, due to the Nanjiang Binxi Avenue Strait Convention and Exhibition Center In order to meet the needs of cleaning construction of the facade of the underpass such as the throughway, in accordance with the provisions of Article 39 of the "Road Traffic Safety Law of the People's Republic of China", it was decided to clean the underpass of the Strait Convention and Exhibition Center on Nanjiang Binxi Avenue, etc. Traffic control will be implemented on the through lane. The notice is as follows:
1. From 23:00 on January 8, 2021 to 6:00 on January 9, 2021, temporary traffic will be implemented on the through lane under the Strait Convention and Exhibition Center on Nanjiang Binxi Avenue in different directions. Control, close one lane for facade cleaning construction, and reserve one lane for vehicle traffic.
2. From 23:00 on January 9, 2021 to 6:00 on January 10, 2021, temporary traffic control will be implemented on the carriageway under Daping Road in different directions, and 1 lane will be closed for facade cleaning construction. Vehicles traveling on the construction road are requested to Pay attention to detours.
3. From 23:00 on January 10, 2021 to 6:00 on January 11, 2021, temporary traffic control will be implemented on the carriageway under Sanjiangkou of Nanjiang Bindong Avenue in each direction. One lane will be closed for facade cleaning construction, and two lanes will be reserved. Driveway for vehicular traffic.
4. From 23:00 on January 12, 2021 to 6:00 on January 13, 2021, temporary traffic control will be implemented on the carriageway under the Fuguang South intersection of Yuanyang Road in each direction. One lane will be closed for facade cleaning construction, and one lane will be reserved. Driveway for vehicular traffic.
5. From 23:00 on January 13, 2021 to 6:00 on January 14, temporary traffic control will be implemented on the carriageway under the Anting intersection of Huagong Road in each direction. One lane will be closed for facade cleaning construction, and one lane will be reserved. Driveway for vehicular traffic.
6. From 23:00 on January 14, 2021 to 6:00 on January 15, 2021, temporary traffic control will be implemented on the carriageway under the intersection in front of Huagong Road. One lane will be closed for facade cleaning construction, and one lane will be reserved. Driveway for vehicular traffic.
7. From 23:00 on January 15, 2021 to 6:00 on January 16, 2021, temporary traffic control will be implemented on the carriageway under Gushan Lower Courtyard on Fuma Road in each direction, and 1 lane will be closed for facade cleaning construction, and 1 lane will be reserved. For vehicle access.
Citizens are requested to arrange their travel routes in advance, pay attention to slow down when passing through construction sections, and pass in an orderly manner in accordance with the instructions of traffic commanders and traffic signs and markings.
hereby notifies
Fuzhou Municipal Public Security Bureau Traffic Management Bureau
January 7, 2021