National Day is 7 days away. It should be a time to enjoy a wonderful holiday, but in order to ensure the progress of customer projects, a group of Hisense siege lions still stick to their posts and insist on "fighting". Let us take a look at these cutest Hisense people. Bar!
West Coast Skynet Project Safe City Product Line Team
Time: October 1st
Location: Building 28, Optics Valley Software Park, Development Zone, closed R&D site
Finally, a loving group photo!
Project Manager Cui Yaoyao
Tianwang project will have its initial inspection at the end of October, and the project construction period is tight. Our entire team was basically on the field during the National Day holiday. Especially in the three days before the holiday, everyone worked hard from 9 a.m. to 9 p.m.
Rizhao Expressway Project (Abbreviation) Implementation Team
Time: October 5
Location: Project Infield Construction Site
Time: October 7
Location: Project Infield Construction Site
Project Manager Sheng Guangxue
Construction Period of Rizhao Expressway Project Implementation We are already very nervous, so our implementation team will definitely have to work overtime during the 7-day holiday, mainly working on the construction of the project's infield, which is also the command center. We usually work from 7 a.m. to 8 or 9 p.m., and you can see from the photos that our progress is quite fast.
Hohhot BRT project implementation team
Time: October 2
Location: 19# station time control switch installation
Time: October 4
Location: Construction site debugging and wiring
Project manager Nie Baoyou
BRT project we are responsible for It is an intelligent system for the platform, but due to delays in civil construction in the early stage, we did not have enough time at this time. During the National Day holiday, a dozen of us have been working overtime to ensure that the tasks are completed as planned.
Guiyang Rail Transit Line 1 communication system project team
Time: October 1, 10:43
Location: Administrative Center Station Platform
Time: October 3, 11:20
Location: Chengxin Road Station Hall
Project Manager Wei Wenqiang
Our project was late in bidding, had many construction systems, and was relatively difficult, so many colleagues had to work overtime during the National Day. During the National Day, everyone went to the site to measure and supervise the progress as usual.
Guiyang City 1.5 Ring BRT System Engineering
Time: October 1
Location: North Railway Station Platform
Time: October 1
Location: Guiyang Century City Dormitory
Time: October 6
Location: Garden Fruit Platform Preliminary Leave the pre-embedded plan to be explained on site
Time: October 6
Location: Finance school platform to confirm the progress of civil construction
Project manager Wu Bo
The BRT project in Guiyang will be launched in December, and now is the busiest time. The site needs to keep up with the progress of the civil construction company at any time and confirm and communicate with the civil construction company to reserve the buried plan. In addition, because the computer room does not meet the conditions, the temporary construction, deployment and testing of the backend software are also being carried out in full swing. Hard work is hard work, but being able to ensure the smooth progress of the project is also hard work.